Case study B for offices to show where automatic sprinklers have the greatest impact
This article was originally published as part of The impact of automatic sprinklers on building design, an independent report produced by WSP, sponsored by the Business Sprinkler Alliance (BSA), published in September 2017.
See also: Case study A for offices to show where automatic sprinklers have the greatest impact.
This example features a four-storey office building located in Manchester with 1,600m2 GIA and fully-glazed facades. The separation distances around the building are:
- Offices 20x20 m2.
- 4 storeys – c. 16m.
- Separation distances are; Northern side 11m, Eastern side 20m, Southern side 12m, Western side 15m.
- Glazed façade.
- Occupancy capacity of the building.
- 2 staircases.
Firstly, the impacts of incorporating an automatic sprinkler system on the fire protection measures are demonstrated in Table 6-4. Secondly, cost analysis of the impacts is conducted in Table 6-5.
[Table 6-4 Impact of sprinklers on the required fire protection measures for Building B]
BUILDING B | Without Sprinklers | With Sprinklers |
Fire-rated façade area required |
Northern side (12.5%) = 40 m2 Southern side (0%) = 0 m2 Eastern side (0%) = 0 m2 Western side (0%) = 0 m2 |
Northern side (0%) = 0 m2 Southern side (0%) = 0 m2 Eastern side (0%) = 0 m2 Western side (0%) = 0 m2 |
Stairs minimum width | 1000 mm Stairs area 24m2 per floor | 1000 mm Stairs area 24m2 per floor |
Structural fire protection rating | 60 minutes | 30 minutes |
Dry risers | 1 | 1 |
[Table 6-5 Cost analysis of incorporating sprinklers in Building B]
BUILDING B
Without Sprinklers
With Sprinklers
£0
£97,600
Façade cost14
Non FR façade= 1,240m2 x £600/m2 = £744,000
60min-FR façade= 40m2 x £1,700/m2 = £68,000
Total = £812,000
Non FR façade= 1,280m2 x £600/m2 = £768,000
Total = £768,000
Structural fire protection cost
60min-FR = 1,600m2 x £21.57/m2
= £34,512
30min-FR = 1,600m2 x £12.38/m2
= £19,808
Rental yields derived from changes to net internal area
0 m2
0 m2
1 x £1,500/landing x 4 floors =
£6,000
1 x £1,500/landing x 4 floors =
£6,000
£852,512
£891,408
Total cost impact of sprinklers
Capital cost impact = £38,896 added to the project cost plan by including sprinklers
Verdict: Installing automatic sprinklers in Building B is shown to add cost to the project and would not be recommended when reviewed against the impacts (cost, aesthetics etc.) reviewed herein. Unless there is another requirement requiring their inclusion (business continuity, property protection).
Reference [14] Glazed fire rated façade assumed required for aesthetic reasons by the client.
[edit] Related articles on Designing Buildings
- Automatic fire sprinkler systems: A good practice guide.
- Automatic sprinkler system design and operation.
- Business Sprinkler Alliance.
- Case study A for offices to show where automatic sprinklers have the greatest impact.
- Costs of water automatic sprinkler systems.
- Design benefits of automatic sprinkler systems granted under approved document B
- Drenchers.
- Fire detection and alarm system.
- Fire detector.
- Fire in buildings.
- Fire protection engineering.
- Fire safety design.
- Overview of automatic sprinkler system design and operation
- Sprinkler systems explained: A guide to sprinkler installation standards and rules.
- Sprinklers.
- The cost efficiency of different combinations of fire protection measures.
- The impact of automatic sprinklers on building design.
- Watermist systems for fire protection in domestic and residential buildings DG 534.
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.