Case study B for offices to show where automatic sprinklers have the greatest impact
This article was originally published as part of The impact of automatic sprinklers on building design, an independent report produced by WSP, sponsored by the Business Sprinkler Alliance (BSA), published in September 2017.
See also: Case study A for offices to show where automatic sprinklers have the greatest impact.
This example features a four-storey office building located in Manchester with 1,600m2 GIA and fully-glazed facades. The separation distances around the building are:
- Offices 20x20 m2.
- 4 storeys – c. 16m.
- Separation distances are; Northern side 11m, Eastern side 20m, Southern side 12m, Western side 15m.
- Glazed façade.
- Occupancy capacity of the building.
- 2 staircases.
|
|
|
Firstly, the impacts of incorporating an automatic sprinkler system on the fire protection measures are demonstrated in Table 6-4. Secondly, cost analysis of the impacts is conducted in Table 6-5.
[Table 6-4 Impact of sprinklers on the required fire protection measures for Building B]
| BUILDING B | Without Sprinklers | With Sprinklers |
| Fire-rated façade area required |
Northern side (12.5%) = 40 m2 Southern side (0%) = 0 m2 Eastern side (0%) = 0 m2 Western side (0%) = 0 m2 |
Northern side (0%) = 0 m2 Southern side (0%) = 0 m2 Eastern side (0%) = 0 m2 Western side (0%) = 0 m2 |
| Stairs minimum width | 1000 mm Stairs area 24m2 per floor | 1000 mm Stairs area 24m2 per floor |
| Structural fire protection rating | 60 minutes | 30 minutes |
| Dry risers | 1 | 1 |
[Table 6-5 Cost analysis of incorporating sprinklers in Building B]
BUILDING B
Without Sprinklers
With Sprinklers
£0
£97,600
Façade cost14
Non FR façade= 1,240m2 x £600/m2 = £744,000
60min-FR façade= 40m2 x £1,700/m2 = £68,000
Total = £812,000
Non FR façade= 1,280m2 x £600/m2 = £768,000
Total = £768,000
Structural fire protection cost
60min-FR = 1,600m2 x £21.57/m2
= £34,512
30min-FR = 1,600m2 x £12.38/m2
= £19,808
Rental yields derived from changes to net internal area
0 m2
0 m2
1 x £1,500/landing x 4 floors =
£6,000
1 x £1,500/landing x 4 floors =
£6,000
£852,512
£891,408
Total cost impact of sprinklers
Capital cost impact = £38,896 added to the project cost plan by including sprinklers
Verdict: Installing automatic sprinklers in Building B is shown to add cost to the project and would not be recommended when reviewed against the impacts (cost, aesthetics etc.) reviewed herein. Unless there is another requirement requiring their inclusion (business continuity, property protection).
Reference [14] Glazed fire rated façade assumed required for aesthetic reasons by the client.
[edit] Related articles on Designing Buildings
- Automatic fire sprinkler systems: A good practice guide.
- Automatic sprinkler system design and operation.
- Business Sprinkler Alliance.
- Case study A for offices to show where automatic sprinklers have the greatest impact.
- Costs of water automatic sprinkler systems.
- Design benefits of automatic sprinkler systems granted under approved document B
- Drenchers.
- Fire detection and alarm system.
- Fire detector.
- Fire in buildings.
- Fire protection engineering.
- Fire safety design.
- Overview of automatic sprinkler system design and operation
- Sprinkler systems explained: A guide to sprinkler installation standards and rules.
- Sprinklers.
- The cost efficiency of different combinations of fire protection measures.
- The impact of automatic sprinklers on building design.
- Watermist systems for fire protection in domestic and residential buildings DG 534.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
























