Carbon emissions reduction target CERT
Contents |
[edit] Overview
The Carbon Emissions Reduction Target (CERT) scheme ran between April 2008 and December 2012 following the Energy Efficiency Commitment 2005-2008. CERT placed a five year commitment on certain electricity and gas suppliers to reduce the carbon emissions within domestic properties.
The main aim of CERT was to contribute to the UK’s commitment to cut greenhouse gases by 12.5% by 2008-2012 under the Kyoto Protocol and Climate Change Act 2008. The overall target was for suppliers to achieve a saving of 293 million lifetime tonnes of carbon dioxide (Mt CO2) by 31 December 2012. By the end of CERT in December 2012, energy companies had achieved a saving of 296.9 Mt CO2 (Ofgem, 2013).
The CERT scheme was followed by The Gas and Electricity (Energy Companies Obligation) Order 2012 (the ECO).
[edit] Background
CERT was implemented by the Electricity and Gas (Carbon Emissions Reduction) Order 2008. Suppliers had to demonstrate that carbon dioxide (CO2) saving measures were being achieved through householders implementing energy efficiency measures.
The energy companies that were obliged to meet the reduction target were:
In addition to the carbon reduction target, the energy companies were required to meet the following three targets:
- At least 40% of the target had to be achieved through uptake by ‘Priority Group’ consumers. These were defined as those aged over 70 years of age or in receipt of certain income-related benefits.
- A saving of 16.2 Mt CO2 had to be met by promotion of energy efficient measures to the ‘Super Priority Group’ consumers. These were defined as those on certain qualifying benefits, for example households in receipt of child tax credits and under an income threshold.
- A saving of 73.4 Mt CO2 had to be met by promoting professionally installed insulation measures.
[edit] Delivery
Ofgem regulated the progress of CERT and reported that 3.9 million homes received professionally-installed loft insulation and 2.6 million households received cavity wall insulation. Other measures implemented included:
- Draught proofing and insulation.
- Shower regulators.
- Solar water heating.
- Small scale combined heat and power (CHP).
- Replacement boilers.
[edit] Scheme outcome
By end of the scheme in December 2012, the energy suppliers had achieved the following (Ref Ofgem, 2013):
- Savings of 296.9 Mt CO2 (equivalent to 101.3% of the overall CERT target). The main target required all the energy companies to meet their main obligations, but two failed and so the main target was not achieved.
- 41.3% of the overall carbon saving was from the Priority Group, against a target of 40%. The Priority Group target required that all energy companies had to meet their Priority Group obligations, but one did not so the target was not achieved.
- Saving of 16.6 Mt CO2 of carbon from the Super Priority Group, which is the equivalent of 102.6% of the 16.2 Mt CO2 target. In order to meet the Super Priority Group target, all energy companies had to meet their Super Priority Group obligations, but one did not so the Super Priority Group target was not met.
- Saving of 75.1 Mt CO2 of carbon (equivalent to 102.3% of the 73.4 Mt CO2 target) by installing measures eligible under the Insulation target. In order to meet the Insulation target, all energy companies had to meet their Insulation obligations, but two failed and so the Insulation target was not met
The majority of carbon saving was achieved through the installation of insulation measures (41%), with lighting measures accounting for 17.3%. Heating savings contributed 10%, appliances 5.9% and the remainder was split between microgeneration and CHP, behavioural measures and demonstration actions.
[edit] Related articles on Designing Buildings Wiki
- Carbon dioxide.
- Carbon emissions.
- Cavity wall insulation.
- Circular Construction in Regenerative Cities (CIRCuIT).
- Climate change act.
- Climate change levy.
- Combined heat and power.
- Green deal.
- Energy companies obligation.
- Insulation.
- Kyoto protocol.
[edit] External references
- The final report of the Carbon Emissions Reduction Target (CERT) 2008-2012, Ofgem 2013.
Featured articles and news
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.





















