[edit] Introduction
Procurement is the process of purchasing goods or services. There are many different routes by which the design, construction and operation of a built asset can be procured.
Build, lease, transfer (BLT) is a form of procurement in which a private contractor builds (and finances) a project on behalf of a public sector partner (or client) and then leases the project back to the client for a predetermined period (referred to as the lease or concession period).
The development is then occupied by the client, who pays rent to the contractor for a minimum term under a leasehold agreement. The level of the rent is generally a function of the total development costs (including land acquisition, design, construction and operating costs).
At the end of this period, the contractor transfers the ownership of the project to the client for a price that was previously agreed.
This is a type of public private partnership (PPP). PPPs are a very broad range of partnerships in which the public and private sectors collaborate for some mutual benefit. PPPs can be arranged with either central or local government.
In theory, one of the benefits of this sort of procurement route is that the contractor has to consider the full life cycle of the development when making design and construction decisions. The drawbacks include the complexity of project agreements, and the difficulty of estimating costs and risks over long periods. Private Finance Initiative (PFI) projects, a form of PPP, have come under significant criticism for not delivering value for money to public sector clients.
[edit] Operations responsibilities
In some instances, the public sector partner may include operations in its BLT arrangement. However, it is more common for the client to handle operations while the contractor takes responsibility for maintenance during the period of the lease. At the conclusion of the concessionary period, maintenance (and operations, if applicable) typically reverts to the client.
This procurement method is sometimes used for healthcare, education and transportation facilities, although it may be suitable for other types of public projects such as roads, bridges, dams, railways, tunnels, and so on, or facilities such as prisons, libraries, leisure centres and so on.
[edit] Similar models
Related forms of procurement (some of which are essentially different descriptions of the same process) include:
- Build, lease, operate, transfer (BLOT) model, in which a private contractor builds a project on leased public land and operates the facility for the duration of the lease; once the lease is completed, ownership is transferred to the public entity or client.
- Build, operate, transfer (BOT), whereby the private organisation does not own the project as an asset, they merely receive a concession to operate it for a period of time. See Build operate transfer BOT.
- Build, own, operate, transfer (BOOT), in which the private organisation undertakes a public project and is then granted the right to own, maintain and operate the project for a set period of time, during which they can draw fees from users of the asset. Once the time period has elapsed, the control of the project transfers to the public sector partner, either freely or for a fee that is stipulated in the original contract.
- Design, build, finance and operate (DBFO), which also assigns the design responsibility to the private organisation.
- Design, build, finance, transfer (DBFT), which is a project delivery method that allows a contractor with expertise in design, construction and financing to be appointed to design, construct and arrange financial resources for the works. This is similar to design build finance and operate (DBFO), other than the contractor eventually transfers ownership of the project back to the client.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.