Advantages of a bill of quantities
A bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by a cost consultant (often a quantity surveyor) that provides project-specific measured quantities of the items identified by drawings and specifications in the tender documentation for construction works.
A bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
At some stage in a project’s procurement process, regardless of the type of contract being used, the works will need to be quantified in order to obtain prices or to value the extent of the work and variations to issue payments. A good and accurate BoQ makes this process much easier and more transparent, and removes the reliance on guesswork. Before construction begins, the BoQ can inform the project budget and the modification of any elements of the design that may be prohibitively expensive. It can also help clarify quantities which means the correct materials can be procured in advance of the works starting.
A BoQ can provide a clear and extensive statement of the work that is to be completed, as well as a reliable base for budget control and accurate cost reporting. It enables the preparation of cash flow forecasts and provides a basis for the valuation of variations, the preparation of interim payments, and the final account.
For tenderers, it helps create a low-risk and low-cost tendering environment, which encourages the submission of competitive bids since the risk is better understood and defined.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Bill.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- CESMM4.
- Common mistakes in bill of quantities.
- Cost plans.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- Taking off.
- Tender.
- Types of bill of quantities.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.