Difference between assignment and novation
Transferring an interest in a construction contract from one party to another can be done by either assignment or novation. The differences are minimal but important to understand, as the assignment of an interest when it could be novated might render one party liable for the contract if the other party is unable to perform their obligations.
Assignment is the right to transfer 'choses in action' defined as 'all personal rights of property which can only be claimed or enforced by action and not by taking physical possession'. This definition includes benefits arising under a construction contract such as right to payment, but not burdens such as the obligation to pay. The definition also includes claims for breach of contract.
A common error is to assume that the right to assign must be agreed as part of a contract, like a novation. Assignment is a unilateral right created by statute, Section 136 of The Law of Property Act 1925 or by the law of equity (law developed by the Chancery Division of the High Court of England and Wales). However, the right to assign can be excluded, or restricted, by contract, for example, it is common in collateral warranties to restrict to one assignment without the written permission of the warrantor.
By comparison, novation is a process in which the contractual rights and obligations are transferred to a third party. The benefits and the burdens can be transferred by a novation agreement, rather than just the benefits as with assignment. In building design and construction, novation normally refers to the process by which design consultants are initially contracted to the client, but are then 'novated' to the contractor.
[edit] Related articles on Designing Buildings
- Alienation covenant.
- Assignment.
- Assignment of choses in action.
- Assignment of debt.
- Collateral warranties.
- Difference between collateral warranties and third party rights.
- Legal and equitable assignment.
- Novation.
- Novation agreement.
- Privity of contract.
- Restrictions on assignment.
- Reverse premium.
- The Contracts (Rights of Third Parties) Act.
Featured articles and news
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.





















Comments