Dayworks in construction
Daywork is a means by which a contractor is paid for specifically instructed work on the basis of the cost of labour, materials and plant plus a mark up for overheads and profit. It is generally used when work cannot be priced in the normal way.
NRM2, RICS new rules of measurement, Detailed measurement for building work defines daywork as; '... the method of valuing work on the basis of time spent by the contractor’s workpeople, the materials used and the plant employed.'
Examples of when daywork may be applied are when unforeseen obstructions are encountered during ground works or when work is instructed for which there are no comparative rates in a bill of quantities.
It is usual for most contracts to contain clauses that provide a method of evaluating variations, additional work and instructions by using existing contract rates and prices. NEC contracts favour pre-agreed sums based on acceptance of a contractor’s quotation.
There are two basic options as to how daywork rates can be priced:
Option A – a percentage addition
- Prime cost to which a percentage is added for overheads, profit and incidental costs.
Option B – all inclusive rates
- All inclusive rates are quoted at tender and incorporated in the contract documents. These include an allowance for overheads and profit, either fixed for the period of the contract, or, in the case of contract conditions that are index linked, subject to an inflation allowance.
[edit] Related articles on Designing Buildings
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
Comments
There is a great mobile phone App that lets you quickly create a daywork or just a resource estimate and send it to the office in minutes, the App date stamps start and finish photos to help you prove the record is a true reflection of the works. It also allows you to quickly get pre-authorisation of the daywork prior to starting the works. Here's the link http://www.constructionrates.co.uk/Rate_Gen/Android_Mobile_Tablet_Smart_Phone_Daywork_App_UK_Construction_Industry.htm