Traditional contract: project brief
This stage is concerned solely with preparing the project brief, the key document upon which the design will be based.
[edit] Starting the work stage and appointing additional members of the consultant team if necessary.
The client updates the business case and project execution plan to reflect comments made at the end of the previous stage. The lead consultant then co-ordinates a start-up meeting attended by the consultant team and the client to issue the revised project execution plan (and business case or part of it if appropriate), to pass on comments made at the end of the previous stage, and to agree the programme for the stage.
The consultant team or the client may identify a requirement to appoint additional consultants or specialist designers. Go to work stage: Traditional contract: appointment.
[edit] Preparing the project brief.
The client and consultant team discuss the required contents of the project brief and consider who the consultant team may need to consult in the preparation of the project brief. It may be appropriate to prepare a project directory of contact details and perhaps a stakeholder map.
The client informs user panels, champions and other stakeholders that will be involved in the development of the project brief that they should make time available to meet with the consultant team. The lead consultant co-ordinates the consultant team to carry out consultations with user panels, champions and other stakeholders and feeds back the outcome of consultations to the client.
The lead consultant co-ordinates the consultant team to prepare a draft project brief.
The client begins preparing, or arranges for the consultant team to begin preparing, a site waste management plan (if required). At this stage, this is a means of recording decisions made to minimise the consumption of resources and to minimise the generation of waste.
The cost consultant highlights areas of potential cost savings and areas of potential cost problems apparent in the draft project brief and prepares an elemental cost plan. The client considers advice from the cost consultant and instructs the consultant team to amend the draft project brief if necessary.
The client issues the revised project brief to the user panels, champions and other stakeholders who may propose further revisions. The client considers the proposed amendments and instructs any necessary revision of the project brief.
If necessary the client revises the business case and project execution plan. This might include: additional value management and risk assessment exercises, re-assessment of the budget and re-assessment of the procurement route.
The project brief is issued to user panels, champions and other stakeholders who may have further involvement in the development of the project.
The client confirms that funding is available and that there is still stakeholder support for the project, and considers whether to proceed to the next stage.
Featured articles and news
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.