Multiple Author ArticleTips for a new BREEAM assessor
Contents |
[edit] Pre-appointment
[edit] Good questions to ask
- Project’s particularities?
- What is the actual stage of the project? Timescale?
- Is a BREEAM AP appointed on the project?
- What is the client’s previous experience with BREEAM, do they understand the process and the role they play.
- What is the BREEAM level targeted? Is it achievable?
- Is BREEAM target a client’s choice or planning requirement?
- What meetings have already taken place? Are there minutes for these?
- What RIBA Stage are we at? Are the RIBA Stage sensitive credits still obtainable?
- Can all the mandatory credits be achieved?
- What steps must be priority?
[edit] Early stages
[edit] Applicable criteria
- Review the site location to see what credits are achieved by default i.e. Ecology, Flood Risk or Transport issues
- Always check for any building specific criteria
- Could this be a ‘Simple Building’?
[edit] Pre-Assessment
- A pre-assessment can be completed on BREEAM Projects.
- What is the desired timescale for completing the pre-assessment?
- If you are aiming for a target rating aim 5% higher than you need. This will help you avoid missing the targeted level because of pitfalls on your project
[edit] Briefing the client
- Make clear to the Team the type of evidential requirements and format
- Be specific and try to avoid quoting large part of the manual. Give similar examples from other projects (you are new so may need to be innovative or have a chat with more senior BREEAM assessor before the meeting)
[edit] Assessment scope
- Check what minimum standards will apply
- Which compliance notes could affect you getting the credits?
[edit] Assessment tools
- It is also possible to use Tracker Plus and IES Tap to create Pre-Assessments and gather evidence throughout the BREEAM assessment.
- Do not dismiss the available reporting tools such as IES TaP and Tracker+, some clients are fans
- Familiarise yourself with available tools and present to the client your opinion on which is the best but ultimately if client wants to use a particular one you should go with client’s selection.
[edit] Consultants
- Advise on early stage consultants that will be required i.e. ecologist, acoustician etc
[edit] Project info
- In order to start an assessment you will need to know the building type, scope of works and rating required
- Review what information is available
- and what stage the project is at to see if any early stage credits are achievable or have been missed
- What's driving the BREEAM assessment (e.g. planning requirement, client intent?)?
- Targeted BREEAM rating (e.g. Very Good, Excellent)
- Confirmation of current RIBA stage
- Budget of project.
- Project directory available listing all design team parties
- What's the type of contract (e.g traditional D&B)?
- Gross internal floor area confirmation.
- M&E design description.
- What is the sustainability approach? Has an LZC report been conducted? Is there an intent for use of renewables or any LZC technologies?
- Understand what has been designed in the scheme to date
- Understand the design and construction programme
[edit] Registration
[edit] During assessment
[edit] General advice
- Some project teams need more support, be proactive and prepare frequent updates but make it clear it’s not your job to win the credit for them
- Seek access to the owner of the building.
- You are an assessor not the AP (probably or in some cases), however it is expected of you to provide explanation or certain degree of support as you are the specialist! You have to be proactive if you want repeat business
- Competent communication with participants of the assessment
[edit] Report completion
[edit] Checklist
[edit] Evidence
- Be as flexible as possible in terms of receiving evidence but ensure they address all the necessary criteria clearly
- Site Inspection Report is the most valuable and robust type of evidence.
[edit] Referencing
[edit] Timescale
- Always check with your clients if they need the certificate by a certain date, you may need to apply for fast track
[edit] Personal qualities
- Be equipped with perseverance.
- Don’t pretend you know all the BREEAM Technical Requirements, nor to be an expert on each discipline (if any). Take time to understand the project and provide answers when you are clear.
- Patience
[edit] Resources
[edit] BREEAM Forum
- If unsure you can always use the Assessor Forum to consult the advice of other assessor’s, we are all always learning with every new project so never feel stupid to ask
[edit] Knowledge Base
- Always consult the Knowledge Base
- The Knowledge Base under BREEAM Projects is very useful source of information
[edit] BREEAM Project Management Tool
- A great tool for tracking your BREEAM projects/ credits is a cloud based tracker called IES TaP: More info can be found here - IES TaP Website
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Multiple Author Article 16:28, 19 Apr 2018 (BST)
Featured articles and news
Celebrating architecture's eloquent champions.
Unusual perspectives on 1960s’ thinking.
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.