Provisional quantity
According to NRM 2, RICS new rules of measurement, Detailed measurement for building works, published by the Royal Institution of Chartered Surveyors (RICS) in April 2012, the term provisional quantity means:
| ...a quantity which cannot be accurately determined (i.e. an estimate of the quantity). |
NRM2 suggests that:
| Where work can be described and given in items in accordance with the tabulated rules of measurement but the quantity of work cannot be accurately determined, an estimate of the quantity shall be given and identified as a ‘provisional quantity’. Work items identified as a ‘provisional quantity’ shall be subject to remeasurement when they have been completed. The ‘approximate quantity’ shall be substituted by the ‘firm quantity’ measured, and the total price for that item adjusted to reflect the change in quantity. Where the variance between the ‘provisional quantity’ and the ‘firm quantity’ measured is less than 20 per cent, the rate tendered by the contractor shall not be subject to review. Where the variance is significant (i.e. 20 per cent or more), the rate can be reviewed to ensure that the rate is fair and reasonable to both the employer and contractor. |
[edit] Related articles on Designing Buildings
Featured articles and news
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.





















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.