Crane supports
Tower cranes are usually supplied on a hire basis, with the client being responsible for the design and construction of the base upon which the crane will be erected. Details of loading are provided by the crane supplier and the base is most commonly designed as a temporary structure, although sometimes a crane base will be incorporated into the permanent structure to save on cost and time.
Loads are given in two forms, ‘in service’ loads, where the crane is functioning and wind speeds are restricted (ie cranes will not operate at high wind speeds), and ‘out of service’ loads, where the crane is not being used but maximum wind speeds may occur.
The location for a crane should be carefully selected to provide a maximum working radius, and when two cranes are being used on the same site mast heights and jib lengths must be considered so that they do not clash.
Cranes are typically structured around two rails at their base between 4.5m-10m apart with wheels in each corner. Cranes are not normally tied down, so sufficient kentledge must be provided to ensure vertical loading from the crane passes through the rails and into the foundation. The foundation is designed so that the unfactored loading from the crane and the unfactored loading from the foundation itself create a bearing pressure which is less than the allowable bearing pressure of the soil.
Various foundation types can be selected depending on the ground conditions:
- Where possible a structural fill can be compacted and used to support a crane with the load spreading through layers of track support at 45° in to the soil strata below.
- When loads from the crane increase, reinforced concrete foundations may be required. This can involve a series of reinforced concrete beams used to support line loads as a result of the crane loading.
- When ground conditions are particularly poor, piled foundations may be necessary. Careful design is required to ensure that reinforcement at the top of the pile top does not cause problems for positioning the mast base section of the crane.
[edit] Related articles on Designing Buildings Wiki
- Avoiding crane collapses.
- Bituminous mixing and laying plant.
- CDM.
- Compressed air plant.
- Concreting plant.
- Construction plant.
- Crane regulations.
- Deleterious materials.
- Designers.
- Design liability.
- Demolition.
- Earth-moving plant.
- Electromagnetic overhead cranes.
- Excavating plant.
- Facade retention.
- Falsework.
- Forklift truck.
- Formwork.
- Gantry.
- Health and Safety.
- Scaffolding.
- Temporary works
- Trench support.
- Types of crane.
[edit] External references
- BS5975:2008 + A1: 2001 Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework (BSI 2011).
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.