Approximate quantities
A development of the elemental cost plan of estimating construction project costs, approximate quantities form part of an approximate quantities cost plan which represents a first attempt to measure defined quantities from drawings (or to ‘take them off’)
An approximate quantities cost plan is part of the iterative cost planning process and is a development of the elemental cost plan. Unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects), the approximate quantities cost plan is a first attempt to measure defined quantities from drawings. In effect, it is a costed approximate bill of quantities.
The approximate quantities method is regarded as being more accurate and reliable than other estimating methods in showing where costs are distributed. In particular, it draws to the attention of designers those elements of the design that are standard and those that are not and which, as a consequence, may be more expensive.
Unlike the elemental method, the basis of the approximate method of estimating is the grouping together of diverse, combined items under a rate (known as a composite rate) which is calculated by combining the individual prices of the components in the group. Because the items grouped together have the same dimensions (whether in metres or square metres, or perimeter and area), it allows those items to be measured at the same time.
For example, under the approximate quantities method, items such as roofs can be grouped with soffits and ceilings; this would not occur in the elemental plan.
The approximate quantities cost plan can form a solid base for an effective value engineering exercise. However, it should be accompanied by a schedule of assumptions made and perhaps a cash flow projection. A pre-construction whole-life cost plan may also be prepared.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.