Site investigation
Approved document C, Site preparation and resistance to contaminants and moisture, suggests that the extent and level of site investigations needs to be tailored to the type of development and the previous use of land.
The approved document suggests that site investigations should consist of four well-defined stages:
- Planning stage: Setting clear objectives for the site investigation, including scope and requirements, which enable it to be planned and carried out efficiently and provide the required information.
- Desk study: Reviewing historical, geological and environmental information about the site.
- Site reconnaissance (a walkover survey): Identifying actual and potential hazards and the design of the main investigation.
- Main investigation and reporting: Including intrusive and non-intrusive sampling and testing to provide soil parameters for design and construction.
Site investigations should include:
- Susceptibility to groundwater levels and flow.
- Underlying geology, and ground and hydro-geological properties.
- Identification of physical hazards.
- Identification of methane and other gases.
- Determining an appropriate design.
- Providing soil parameters for design and construction.
Where a site may be affected by contaminants, a combined geotechnical and geo-environmental investigation should be considered and remediation maybe necessary.
It may also be necessary to notify findings to regulatory authorities, for example:
- Where contaminants are found that had not been previously known about.
- In planning applications.
- In relation to waste management and the protection of water quality and resources.
[edit] Related articles on Designing Buildings
Featured articles and news
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.