Site selection and acquisition for construction
Site selection and acquisition is crucial when the client does not own the site to be developed. It should be undertaken as early as possible, ideally, in parallel with feasibility studies. This work may be carried out by a specialist consultant.
Key to the process is ensuring that the requirements for the site are properly defined, that the selected site meets these requirements and that it is acquired within the constraints of the project programme and with minimal risk to the client.
To achieve these objectives the following tasks need to be carried out:
- Preparing a statement of objectives/requirements for the site and facility/buildings and agreeing this with the client.
- Preparing a specification for site selection, establishing the criteria for evaluating sites based on the objectives/requirements and agreeing weightings with the client.
- Establishing the outline funding arrangements.
- Determining responsibilities within the project team (client/project manager/commercial property agent).
- Appointing/briefing members of the team and developing a schedule for site selection and acquisition; monitoring and controlling progress against the schedule.
- Actioning site searches and collecting data on sites, including local planning requirements, for evaluation against the criteria. See technical due diligence and site appraisals for more information.
- Evaluating sites against the criteria and producing a short list of three or four.
- Establishing initial options and developing costs.
- Discussing short-listed sites with relevant planning authorities.
- Obtaining advice on the approximate open-market value of short-listed sites.
- Selecting the preferred site from the short list.
- Appointing agents for price negotiation and separate agents for independent valuation.
- Appointing lawyers as appropriate.
- Determining specific financial arrangements.
- Exchanging contracts for site acquisition once terms are agreed, conditional upon relevant matters, such as ground investigation, planning consent and so on.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Related articles on Designing Buildings Wiki
- Applying for new postal addresses.
- Building People.
- Condition survey.
- Contaminated land.
- Developer.
- Gross development value.
- Ground conditions.
- Land acquisition.
- Overage.
- Overbuild.
- Restrictive covenants.
- Right of way.
- Site appraisal.
- Site information.
- Site surveys.
- Soil survey.
- Technical due diligence.
- Vacant possession.
- What is a housing start?
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.