Site selection and acquisition for construction
Site selection and acquisition is crucial when the client does not own the site to be developed. It should be undertaken as early as possible, ideally, in parallel with feasibility studies. This work may be carried out by a specialist consultant.
Key to the process is ensuring that the requirements for the site are properly defined, that the selected site meets these requirements and that it is acquired within the constraints of the project programme and with minimal risk to the client.
To achieve these objectives the following tasks need to be carried out:
- Preparing a statement of objectives/requirements for the site and facility/buildings and agreeing this with the client.
- Preparing a specification for site selection, establishing the criteria for evaluating sites based on the objectives/requirements and agreeing weightings with the client.
- Establishing the outline funding arrangements.
- Determining responsibilities within the project team (client/project manager/commercial property agent).
- Appointing/briefing members of the team and developing a schedule for site selection and acquisition; monitoring and controlling progress against the schedule.
- Actioning site searches and collecting data on sites, including local planning requirements, for evaluation against the criteria. See technical due diligence and site appraisals for more information.
- Evaluating sites against the criteria and producing a short list of three or four.
- Establishing initial options and developing costs.
- Discussing short-listed sites with relevant planning authorities.
- Obtaining advice on the approximate open-market value of short-listed sites.
- Selecting the preferred site from the short list.
- Appointing agents for price negotiation and separate agents for independent valuation.
- Appointing lawyers as appropriate.
- Determining specific financial arrangements.
- Exchanging contracts for site acquisition once terms are agreed, conditional upon relevant matters, such as ground investigation, planning consent and so on.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Related articles on Designing Buildings Wiki
- Applying for new postal addresses.
- Building People.
- Condition survey.
- Contaminated land.
- Developer.
- Gross development value.
- Ground conditions.
- Land acquisition.
- Overage.
- Overbuild.
- Restrictive covenants.
- Right of way.
- Site appraisal.
- Site information.
- Site surveys.
- Soil survey.
- Technical due diligence.
- Vacant possession.
- What is a housing start?
Featured articles and news
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.