Provisional quantity
According to NRM 2, RICS new rules of measurement, Detailed measurement for building works, published by the Royal Institution of Chartered Surveyors (RICS) in April 2012, the term provisional quantity means:
...a quantity which cannot be accurately determined (i.e. an estimate of the quantity). |
NRM2 suggests that:
Where work can be described and given in items in accordance with the tabulated rules of measurement but the quantity of work cannot be accurately determined, an estimate of the quantity shall be given and identified as a ‘provisional quantity’. Work items identified as a ‘provisional quantity’ shall be subject to remeasurement when they have been completed. The ‘approximate quantity’ shall be substituted by the ‘firm quantity’ measured, and the total price for that item adjusted to reflect the change in quantity. Where the variance between the ‘provisional quantity’ and the ‘firm quantity’ measured is less than 20 per cent, the rate tendered by the contractor shall not be subject to review. Where the variance is significant (i.e. 20 per cent or more), the rate can be reviewed to ensure that the rate is fair and reasonable to both the employer and contractor. |
[edit] Related articles on Designing Buildings
Featured articles and news
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.