Preliminary business case for construction project
The preliminary business case sets out a justification for the investment that would be required by a potential development. It is used to decide whether the potential project merits being investigated in more detail.
A preliminary business case should be prepared very early in the project, before any decision has been made to proceed. It allows the client to explore high level options for meeting the requirements set out in the statement of need. This may include an assessment of comparable projects.
Experienced clients may have in-house expertise allowing them to prepare a preliminary business case. However, some clients will not have the full range of skills required and may wish to appoint independent client advisers to assist them.
A preliminary business case may include:
- Funding options.
- Legal agreements.
- Management structure.
- Objectives and mission statement.
- An assessment of constraints.
- Alternative solutions, such as refurbishment, or changing operational practices.
- A summary of options considered and discarded.
- Assessment of the main hurdles to surmount, show-stoppers, uncertainties and risks.
- Assessment of previous similar projects and lessons learned.
- Assumed procurement route.
- Assumed programme and phasing.
- A schedule of consultants that will be required.
- The market and competition.
- The budget, inclusions and exclusions and contingency allowance.
- A description of the business needs, benefits and keys to success and value.
- Public relations and external communications strategy.
- An assessment of any political consequences of the project.
- An assessment of the likely costs for the next stage.
- A proposal for the way forward.
- Relevant research, including assessment of similar facilities.
The preliminary business case is likely to be in a report format, however, where possible, information and requirements should be scheduled in a database or spreadsheet format that will be easy to expand and will be easy to use to test whether proposals satisfy requirements later in the project.
When, or if consultants are appointed, the preliminary business case should be updated to include their feedback and recommendations.
Once feasibility studies and options appraisals have been carried out by the consultant team, the preliminary business case should be developed into a full business case for the preferred option. The full business case is the document that will be used to obtain authority for the preferred option to progress to concept design.
[edit] Related articles on Designing Buildings Wiki
- Benchmarking.
- Budget.
- Business case.
- Cash flow.
- Client requirements.
- Constraints.
- Contingencies.
- Cost plans.
- Development appraisal.
- Feasibility studies.
- Funding options.
- Funding prospectus.
- Mission statement.
- Options appraisals.
- Risk.
- Risk management.
- Risk register.
- Whole-life costs.
[edit] External links
- OGC guidance on business cases.
- HM Treasury: Green Book, a framework for the appraisal and evaluation of projects.
Featured articles and news
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Update on the future of Grenfell Tower
Deputy Prime Minister decides for it be carefully taken down to the ground.
Ending decades of frustration, misinformation and distrust.
Essential tools in managing historically significant landscapes.
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.