Plan, Do, Check, Act (PDCA)
Plan, Do, Check, Act (PDCA) is a model that is used to assist the control and continual improvement of processes and projects. It has been used in construction project management as a means of balancing the systems and behavioural aspects of management and health and safety. Its cyclic approach allows for the constant updating of health and safety measure ultimately leading to a safer working environment.
PDCA was popularised by W. Edwards Deming, a leading figure in modern quality control processes and procedures. Deming intended that PDCA should be used when developing a new or improved process, product or service; when implementing changes; when defining a repetitive work process, and so on.
It is made up of the following stages:
- Plan: Assess a current or new process and how improvements could be made.
- Do: Test small changes as part of a limited study to assess their effectiveness.
- Check: Gather and analyse the test results, compare them with the expected outcomes and identify what has been learnt.
- Act: Take action according to the lesson learned in the ‘Check’ step.
In some iterations of PDCA, the fourth step ‘Act’ is replaced with ‘Adjust’. This is often used when the PDCA process has been run several times and enough information has been accumulated for it to have been adopted as a new ‘standard’. ‘Adjust’ allows for continual monitoring of the process after changes have been made, with small improvements as and when appropriate, creating a cycle of continuous improvement.
[edit] Related articles on Designing Buildings
- Assurance and self-certification.
- CDM Regulations: a quality perspective.
- Contingency theory.
- Continuous improvement process.
- Design freeze: a quality perspective.
- Digital engineering.
- Game theory.
- Lean construction.
- Lean Six Sigma.
- Pareto analysis.
- Project execution plan.
- Project manager.
- Quality control.
- Quality Management System.
- Total quality management in construction.
- Transition time.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments
This doesn't seem have been developed for practical application in a construction environment.