PPN 021: Payment Spot Checks in Public Sub-Contracts
PPN 021: Payment Spot Checks in Public Sub-Contracts. This PPN sets out how contracting authorities can spot check their public contract supply chains to ensure suppliers meet the payment terms in the Procurement Act 2023.
After consultation with ECA’s leadership role on payment and in response to ECA’s call for more robust monitoring and enforcement of payment requirements, Cabinet Office has published PPN 021.
This PPN encourages contracting authorities to ‘spot check’ their suppliers to ensure that 30-day payment terms are being implemented throughout the supply chain on public sector contracts with a value over £5 million per annum. A term was made a requirement under the Procurement Act 2023 (implemented on 24 February 2025) after work by ECA to introduce mandatory 30-day payment in public sector contracts at tiers 1 and 2 of the supply chain.
From 1 October 2025, public sector authorities should include terms within their contracts to enable them to undertake payment spot checks and request the following information from suppliers at least once every six months:
- A copy of the payment terms for the contract.
- Details of procedures for resolving disputed invoices promptly and effectively and evidence that these have been shared with the supply chain.
- Evidence of payments made (and time taken to pay) in relation to the contract.
Most of this information will be easily extracted form digital payment management systems.
If it is discovered that a supplier is not complying with the requirement to pay within 30 days, a public sector contracting authority may take a number of actions.
This PPN sets out how contracting authorities can spot check their public contract supply chains to ensure suppliers meet the payment terms in the Procurement Act 2023.
This article appears on the ECA news and blogsite as 'ECA Influence: Monitoring Payment Performance' dated 1 May, 2025.
--ECA
[edit] Related articles on Designing Buildings
- Best value procurement.
- Cabinet office payment rules within the procurement act welcomed.
- Common minimum standards.
- Dynamic purchasing system under the Single Procurement Document (Scotland).
- Fair payment practices.
- Independent review of construction frameworks.
- Infrastructure and Projects Authority.
- Integrated Supply Team.
- Management Consultancy Framework MCF.
- Managing the procurement process.
- Major Projects Authority.
- Output-based specification.
- Procurement Act 2023.
- Procurement Policy Note 12/15.
- Procurement policy note PPN.
- Procurement route.
- Public procurement.
- SMEs and government contracts.
- Sourcing playbook.
- Transforming Public Procurement Green Paper.
- Cabinet office payment rules within the procurement act welcomed.
Featured articles and news
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.