Nominated supplier
In the construction industry, ‘supplier’ is a very general term which refers to organisations contracted as part of the delivery of a built asset.
Typically, a contractor is able to purchase from their own choice of supplier, as long as they comply with the requirements set out in the specification. However, under certain circumstances, the client may wish to impose (or nominate) a particular supplier on the main contractor after the main contractor has been appointed.
The client may wish to use a particular supplier because:
- A particular product brand is required.
- The particular goods provided by the supplier are not widely available.
- There is an existing relationship with the supplier.
- Long delivery items are required where ordering is necessary before the appointment of a main contractor.
- Specialist design input is required in the early stages of design development.
- Complex or specialist industrial plant or equipment may be required, upon which the design will be based.
The mechanism for nominating is an instruction in relation to a prime cost sum to which the main contractor is entitled to add mark up and attendance costs. This allows the client to have direct separate negotiations with suppliers and feed their appointment into the contract after works by the main contractor have commenced.
A potential drawback of nominating a supplier is that the contractor is then not able to ‘shop around’ to obtain the best price or supplier. It is important therefore that suppliers are nominated with due consideration to their ability to supply in line with the project specification, programme and budget.
In addition, as the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for their failure to perform. However, as the supply contract is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated supplier to guarantee performance and indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
The complexity of this situation means that some forms of contract no longer include provision for the nomination, preferring to 'name' suppliers instead.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.