Dutch auctions in the construction industry
Contents |
[edit] Introduction
A Dutch auction is also known as an open descending bid. It is a procurement method in which an inflated price is set at the start of the process and is then progressively lowered until a bidder is prepared to make an offer. This purchasing approach can be used to procure construction services.
[edit] History
This is a procurement method that has been throughout the history of commerce. In the 17th century, the method became associated with estate and painting sales in Holland. In the Netherlands, Dutch auctions are referred to as Chinese auctions.
Dutch auctions came to England in the 18th century, although at the time, they were referred to as ‘mineing auctions'. This was due to the fact the auction continued until the price dropped and a bidder shouted out the word, ‘Mine’.
[edit] Strategy
For bidders, it is essential to have an accurate sense of the value of the service that is being auctioned. This is sometimes referred to as rational bidding. A rational bid of this kind may factor in hidden costs known only to the bidder which will project that amount onto the value of the service.
Dutch auctions are generally considered to be an efficient procurement method, although they are not frequently used on construction projects. The method is primarily used when new companies make initial public stock offerings.
Dutch auctions are also referred to as multiple item auctions (since they allow services to be bundled together) or clock auctions. While Dutch auctions are similar to reverse auctions, there is a specific Reverse Dutch Auction where the price of the items starts low and then increases in set intervals.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.