Open tendering of construction works
A 'tender' is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. In construction, the main tender process is generally the selection, by the client, of a contractor to construct the works. However, procurement routes have become more complex, so tenders may now be sought for a wide range of goods and services.
Irrespective of the goods or services that are being sought, securing tenders generally follows one of a number of basic procedures:
Open tendering allows anyone to submit a tender to supply the goods or services that are required. Generally, an advert will be placed giving notice that the contract is being tendered, offering an equal opportunity to any organisation to submit a tender.
On larger projects, there may then be a pre-qualification process that produces a short-list of suitable suppliers from the respondents expressing interest in the contract. This short list will then be invited to prepare tenders. The selection of a short list can include pre-qualification questionnaires and interviews. This sort of pre-qualification process is not the same as selective tendering. Selective tendering only allows suppliers invited from a pre-selected list to take part in the tender process.
Open tendering has been criticised for being a slow and costly process, attracting tenders or expressions of interest from large numbers of suppliers, some of whom may be entirely unsuitable for the contract and as a result it can waste a great deal of time, effort and money. However, open tendering offers the greatest competition and has the advantage of allowing new or emerging suppliers to try to secure work and so can facilitate greater innovation. The number of firms tendering can be reduced (ideally to a maximum of 6) by a pre-qualification process, and if this uses a standard pre-qualification questionnaire, then the time wasted by unsuitable applicants can be minimised.
Whilst often seen to be more efficient, selective tendering can exclude potential suppliers, it can be seen to introduce bias into the process, and it can result in prospective suppliers continually contacting clients and consultants to check that they are on the appropriate lists.
On public projects, or projects that include an element of public funding, it may be necessary to advertise contracts as a requirement of the Public Contracts Regulations. This is intended to open up public procurement within the European Union and to ensure the free movement of supplies, services and works (see OJEU for more information).
Open tendering can be either single stage or two stage. Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed, allowing them to begin work and ine a fixed price is negotiated for the contract.
For a more detailed description of the procedures for open tendering, see Tender.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Call-off contract.
- Due diligence when selecting contractors or subcontractors.
- E-tendering.
- Invitation to tender.
- Mid-tender Interviews.
- OJEU procurement rules.
- Pre-qualification questionnaire.
- Pre-tender Interviews.
- Procurement routes.
- Reverse auction.
- Selective tender.
- Tender documentation.
- Tender evaluation.
- Tender processes for construction contracts
- Tender.
- Two stage tender.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.