Selective tendering
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. In construction, the main tender process is generally the selection, by the client, of a contractor to construct the works. However, as procurement routes have become more complex, so tenders may be sought for a wide range of goods and services.
Irrespective of the nature of the goods or services that are being sought, securing tenders generally follows one of a number of basic procedures:
- Open tendering.
- Selective tendering.
- Negotiated tendering.
- Serial tendering.
- Framework tendering.
Open tendering allows anyone to submit a tender to supply the goods or services that are required, generally in response to an advert giving notice that the contract is being tendered. On larger projects, there may then be a pre-qualification process that produces a short-list of suitable suppliers who will be invited to prepare tenders. This sort of pre-qualification process is not the same as selective tendering.
Selective tendering only allows suppliers to submit tenders by invitation. A pre-selected list of possible suppliers is prepared that are known by their track record to be suitable for a contract of the size, nature and complexity required. They might then be asked if they would be interested in tendering for the contract, and then based on the responses received, a number of them invited to tender (generally no more than 6). From the tenders received, a preferred tenderer is selected based on criteria such as price and quality and negotiations entered into.
Consultants or experienced clients may maintain ‘approved’ lists of prospective suppliers appropriate for particular types of contract and then regularly review performance to assess whether they should remain on the list.
Selective tendering may be particularly appropriate for specialist or complex contracts, or contracts where there are only a few suitable firms. Selective tendering will tend to be faster than open tendering, and can be seen as less wasteful, as there is no pre-qualification process as part of the tender procedure itself, and only suppliers that are known to be appropriate for the proposed contract are invited to prepare tenders. It can also give clients greater confidence that their requirements will be satisfied.
However, it can exclude smaller suppliers or those trying to establish themselves in a new market, it can reduce the potential for innovation, and it can be seen to introduce bias into tendering as firms may be excluded from approved lists for unknown reasons, because of a lack of awareness, or because of personal preferences. It can also result in prospective suppliers continually contacting clients and consultants to check that they are on the appropriate lists.
On public projects, or projects that include a publicly-funded element it may be necessary to advertise contracts. This is a requirement of the Public Contracts Regulations, intended to open up public procurement within the European Union and to ensure the free movement of supplies, services and works (see OJEU for more information).
Selective tendering can be either single stage or two stage. Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed allowing them to begin work and in the second stage a fixed price is negotiated for the contract.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Common mistakes in construction tenders.
- Due diligence when selecting contractors or subcontractors.
- E-tendering.
- How to prepare tender documents.
- Invitation to tender.
- Mid-tender Interviews.
- OJEU procurement rules.
- Pre-qualification questionnaire.
- Pre-tender Interviews.
- Procurement routes.
- Tender documentation.
- Tender evaluation.
- Tender processes for construction contracts
- Tender.
- Tender settlement.
- Things to avoid when tendering.
- Two stage tender.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.