Sequential test
A flood risk assessment is required for most proposed developments that are within a designated flood zone.
A sequential test may be required as part of a flood risk assessment. It compares the site for a proposed development with other available sites to determine which has the lowest flood risk.
A sequential test is required if:
- The development is in flood zone 2 or 3, AND
- A sequential test has not already been done for a development of the type proposed on the proposed site.
A sequential test is not required if:
- The development is a ‘minor development’ OR
- The development involves a change of use, unless it is a caravan, camping chalet, mobile home or park home site OR
- It is a development in flood zone 1, unless there are flooding issues in the area of the development.
The sequential test must conclude whether any of the alternative sites that have been identified have a lower risk of flooding than the proposed site. It should be submitted along with the flood risk assessment and the planning application to the local planning authority.
If the sequential test shows that it is not possible to use an alternative site, it may be necessary to undertake an exception test. This shows how flood risk will be managed on the proposed site and demonstrates that the sustainability benefits of the development to the community outweigh the flood risk.
For more information see: https://www.gov.uk/guidance/flood-risk-assessment-the-sequential-test-for-applicants
[edit] Related articles on Designing Buildings Wiki
- BREEAM Flood risk management.
- BREEAM Surface water run-off.
- Design flood event.
- Design flood level.
- Flood and Water Management Act.
- Flood defences
- Flood plain
- Flood risk
- Flood risk assessment.
- Flood risk management plan
- Flood zone
- Flood.
- Minor development.
- Planning for floods.
- Property flood resilience
- Sustainable urban drainage systems.
Featured articles and news
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.