Contingency plan
Contingency plans are plans than could be enacted to mitigate project risks identified during risk assessment, if those risks increase or materialise. That is, they are alternative courses of action devised to cope with project risks.
Predictable risks that could be mitigated with forward planning might include:
- Non-delivery of materials. An alternative design might be prepared, or bulk or specific items could be pre-ordered before contractors are appointed
- Lack of available work force. This could be tackled by the provision of a site labour camp or by overseas recruitment.
- Lack of plant and equipment availability (or plant failure or access to spare parts). Plant such as piling rigs and spares could be ordered during the design stages prior to contractor involvement.
- Illness. This could be mitigated by insurance cover for key personnel.
- The risk of obtaining planning permission or other statutory approvals. This might be mitigated by early consultation with statutory authorities prior to design, or by employing ex-statutory authority employees, or consultants familiar with the statutory authority.
- Information and communications technology failure. This might be mitigated by duplicating facilities, establishing back-up procedures and providing uninterrupted power supplies.
- Failure of power or water supply. This might be mitigated by the duplication of supply, uninterrupted power supplies or the provision of standby generators.
NB Functional Standards Common Glossary, published by the Cabinet Office, defines contingency planning/ plans as: ‘A course of action and resulting document(s) that prepares the organisation to respond effectively to future significant events, incidents and risks.’
[edit] Related articles on Designing Buildings
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.