Construction management: occupation and defects liability period
The occupation and defects liability period takes place after the client has taken possession of the development for occupation. During this stage, any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, and the construction manager no longer has possession of the site, close co-operation is required between the construction manager and the client so as so not to disturb occupants, whose activities will take priority over trade contractors rectifying defects.
[edit] Starting the work stage.
The construction manager arranges a start-up meeting to plan the work stage.
On construction management contracts, a separate certificate of practical completion is issued for each trade contract. This means that defects liability periods may be at different times for each trade contract and as a consequence, the construction manager may continue to hold construction progress meetings and issue construction progress reports for continuing trade contracts and may have to protect completed work from continuing work.
[edit] Rectifying defects.
If the contract allows, the construction manager may review all relevant events that might be considered to have affected the completion date for each trade contract and may adjust their completion dates accordingly.
The client reports any defects in the works to the construction manager. On large projects the construction manager may set up a hot desk for responding to any complaints or to provide assistance required by the incoming occupants. The construction manager takes advice on the action necessary to rectify the defects from the consultant team, and the construction manager and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary for the client to re-appoint the principal designer (whose appointment may have terminated on certification of project completion) and it may be necessary to amend the health and safety file.
At the end of the defects liability period for each trade contract, the construction manager arranges inspections of the works and prepares a schedule of defects which is issued to the trade contractor. The construction manager agrees the programme for rectification of items on the schedule of defects with the client and trade contractors, which should in any event be rectified within a reasonable time.
The trade contractor rectifies items listed on the schedules of defects, informs the construction manager and provides the construction manager with information for the preparation of the final account. The trade contractor and construction manager agree the final account for the trade contract.
The construction manager arranges final inspections of the trade contractors works and if satisfied issues a final statement (payment notice) for that trade contract. If the client intends to pay a different amount from that shown on the statement, then construction manager must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The client makes payment by the final date for payment. This may include the release of any remaining retention if applicable.
The construction manager completes the building owner's manual.
If a site waste management plan has been prepared, the construction manager may reconcile the planned handling of waste against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
Once final statements have been issued for each trade contract, the construction manager co-ordinates preparation of the final report and issues the final certificate for the project.
Issuing the final certificate will normally signify the end of the construction manager's and consultant team's appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.