Construction stage report
The construction stage report is prepared by the contract administrator at the end of the construction stage. It might include:
- Minutes of the final construction progress meeting.
- Relevant parts of progress reports from the contractor and where appropriate the consultant team.
- Relevant parts of the cost consultant's report.
- A summary of the progress made in each key area of the project.
- Analysis of progress against the programme.
- An explanation of the causes of any delays.
- Progress photos.
- Analysis of key performance indicators.
- An assessment of any quality issues.
- Reports on health and safety issues.
- Reports of any issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety etc).
- Reports about off-site fabrication and off-site payments.
- Earned value analysis.
- An assessment of any design issues.
- An assessment of any other issues that need to be addressed and proposals for addressing them.
- Any instructions required from the client.
- Details of handover procedures.
- Where appropriate, details of phased completion, and partial or sectional handover.
- Any terms or qualifications that will be applied to the certificate of practical completion.
- A proposed schedule of defects.
- Details of any ongoing works by others.
- Insurance details.
- Any remaining access issues.
The report should highlight any instructions required from the client.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
From medieval scribes to modern word art.
Electrical contractors welcome crackdown on late payment and push for clean energy.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.
Setting Expectations on Competence Management
Industry Competence Committee.
New Scottish and Welsh governments
CIOB stresses importance of construction after new parliament elections.
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.