Permission
In general, the term 'permission' refers to allowing, consenting or authorising something.
In relation to property, permissions sometimes take the form of easements or the rights that certain parties have, such as a right of way (permission to enter another’s land), right to light, right of support, and so on. For more information, see Easements.
In the construction industry, it is most relevant in relation to planning. Planning permission is the legal process of determining whether proposed developments should be permitted, and it can present the greatest risk on a construction project.
Section 57 of the Town and Country Planning Act 1990 states that all developments fitting the description of such require planning permission. The developer has the responsibility for ensuring any necessary permissions and permits are in place before works begin.
However, development does not in all instances require planning permission. In England and Wales, the Town and Country Planning (General Permitted Development) Order 1995 enables central government to permit certain types of developments known as permitted developments. These are generally minor changes to existing properties. Permitted developments do not require approval from the local planning authority as permission is granted by the Order.
A Local Development Order, Neighbourhood Development Order or a Community Right to Build Order are other forms of permission that are granted.
A Development Consent Order (DCO) is the means of obtaining permission for developments categorised as Nationally Significant Infrastructure Projects (NSIP). This includes energy, transport, water and waste projects.
Other permissions or consents that may need to be obtained before carrying out development include:
- Works to protected trees.
- Advertisement consent.
- Listed building consent.
- Hazardous substances consent.
- Environmental permits/licences.
- Building regulations approval.
- Permit to work.
- Environmental consents.
- F10 notification.
- Party wall agreements.
For more information see: What approvals are needed before construction begins.
The Housing and Planning Bill 2015 included measures to introduce a 'permission in principle' (PiP) on land allocated for development in a qualifying document such as a brownfield register, development plan or neighbourhood plan. For more information, see Permission in principle.
Developments may not be used for purposes that are not within the use class for which they received planning permission. Planning permission is not needed to change the use of a development when the current use and the proposed use are within the same class. Changing the use of a development from one class to another may require planning permission, however, some changes are considered to be ‘permitted developments’ that are allowed without the need for a planning application.
For more information, see Change of use class.
[edit] Related articles on Designing Buildings Wiki
- Building regulations.
- How long does planning permission last.
- Material amendment to planning permission.
- Non-material amendment to planning permission.
- Permission for felling or lopping a tree
- Permission for mining or working of minerals
- Permission in principal
- Planning permission.
- Prior approval.
- Retrospective planning permission.
- Revocation of planning permission
- What approvals are needed before construction begins.
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.