Purchase orders in construction
A purchase order (PO) is a document that is issued by a buyer to a seller, indicating their intention to purchase certain products or services. On construction projects, POs are typically used to control the purchasing of products and services from suppliers, and are then retained for record keeping.
A PO may include the following information:
- The PO number.
- A description of the products and / or service being purchased.
- Technical details if required.
- Quantities.
- Any discounts to be applied.
- Agreed prices.
- Payment terms.
- Shipment dates.
A PO may be a legally-binding agreement where there is no existing contract, it is only when the supplier accepts the PO that it become a legal contract.
Invoices are documents issued by a suppliers to buyers, summarising the products or services that they have purchased (or have agreed to purchase). Invoices invoice will usually reference a PO number (if there has been one) to assist with record keeping and avoid confusion.
NB A blanket purchase order is: 'A special purchase order typically designed to leverage repetitive requirements and emergency repairs involving low value goods and services, while reducing the administrative workload.' Ref UN Procurement Practitioner's Handbook, produced by the Interagency Procurement Working Group (IAPWG) in 2006 and updated in 2012
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Grenfell Tower community update
Memorial columns to be retained as careful dismantling continues.
When buildings reflected the local resources available.
CIOB reports 57% are using artificial intelligence technologies.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.