Traditional procurement method
Contents |
[edit] What is the traditional procurement route?
The traditional procurement route involves separating design from construction. The client first appoints consultants to design the project in detail (and often to ensure cost control and inspect the construction works as they proceed), and a contractor is then appointed for the construction of the project on a single-stage competitive basis.The contractor’s responsibilities include workmanship, materials and work undertaken by suppliers and subcontractors. They are not responsible for the design (other than temporary works), although some traditional contracts may allow the contractor to design specific parts of the works.
Traditional procurement is typically undertaken under a lump sum contract. A single ‘lump sum’ price for all the works is agreed before the works begin, then stage payments are made as the works proceed. This is appropriate where the project is well defined when tenders are sought, and significant changes to requirements are unlikely. This allows the contractor to accurately price the works they are being asked to carry out.
[edit] How popular is the traditional procurement route?
Traditional procurement remains the most commonly-used method of procuring building works.
The National Construction Contracts and Law Report 2018, published by NBS, suggested the following mix of procurement routes in the construction industry:
- Traditional procurement 46%
- Design and build 41%
- Partnering / alliancing 3%
- Construction management 3%
- Contractor approved without any tender process 2%
- Measured term 1%
- PFI / PPP 1%
- Cost plus 1%
- Management contracting 1%
For more information see: What is the most common procurement route?
[edit] When is the traditional procurement route appropriate?
The traditional procurement route is generally suitable where the client wishes to retain control over decisions relating to the design and quality of the project. However, a full package of detailed information is required before a contractor can be appointed, and this can make it slower and more expensive than some other forms of procurement. It also means that the contractor is not involved in the design decisions, and so it can result in issues with buildability.
[edit] What are the key characteristics of the traditional procurement route?
Key characteristics of traditional procurement include:
- Consultants retaining control over design and quality. This may result in a higher standard of project than some other procurement routes.
- Consultants are responsible for valuations and agreeing payments.
- The contractor generally has no design duties, but where this is necessary for some aspect of a project, the contract should include clear wording to this effect.
- There must be adequate time before tenders are invited to allow for the production of a complete set of drawings and other documents. This means the traditional procurement route may be slower than some other routes.
- Contractors may submit claims if they do not receive the timely instructions and information, or if changes are made.
- The traditional method – or adaptations of it – can be used with approximate quantities, provisional sums or cost reimbursements where the nature or quantity of work cannot be accurately defined.
For further information see Traditional contract for construction.
For other methods see: Procurement routes.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Bill of quantities.
- Construction contract.
- Contract conditions.
- Contractor.
- Notifications during construction works
- Procurement route.
- Temporary works.
- Tender.
- Tender documentation.
- Traditional contract for construction
- Traditional contract: outline work plan.
- Traditional contract - pros and cons.
- Two-stage tender.
- Variations.
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.




























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.