Scope of work
The Association for Project Management describes ‘scope’ as ‘The totality of outputs, outcomes and benefits and the work required to produce them’ and ‘scope management’ as ‘The process whereby outputs, outcomes and benefits are identified, defined and controlled’.
In construction, the term ‘scope of work’ (sometimes described as a ‘scope of works’, ‘statement of work’ or 'terms of engagement') is a very general, and sometimes ambiguous term referring to a general description of the work that is expected to be performed under a particular contract. It may be prepared by the client or their consultants and included in tender documentation for construction works.
The nature of the scope of work can vary significantly from project to project. Sometimes it will simply offer a very broad description of the works required, whilst sometimes it provides a complete description of the project, significant milestones, a programme of work with the expected time frames for delivery, reports, pricing, deliverables, roles and responsibilities and end products that are to be provided.
For more information, see What should be included in a scope of work?
A scope of work can be a useful way of agreeing broad project requirements for both the client and supplier. However, errors or inconsistencies with other contract documentation can lead to confusion and uncertainties which are often cited as a cause of disputes on construction projects.
It is common for changes to be required to the scope of work after the contract has been awarded. Most forms of contract make provisions for the contract administrator to instruct reasonable variations which may give rise to additions or deductions from the contract sum, however, these variations must not change the nature of the works themselves. In some cases, the works may be tendered before the scope of work is known in detail. In this case, provisional sums may be included in the contract, or flexible procurement routes adopted such as measurement contracts or prime cost contracts.
The term ‘scope of work’ is generally used to refer to construction activities, however, a ‘scope of services’ which describes the services a consultant will be performing on a project may also sometimes be referred to as a scope of work.
Confusingly, the term ‘scope of work’ can also used interchangeably with the term ‘schedule of work’. However, a schedule of work has a more specific meaning, referring to 'without quantities' instructional lists often produced on smaller projects or for alteration work as an alternative to bills of quantities, allowing the pricing of items such as builders work and fixing schedules.
[edit] Related articles on Designing Buildings Wiki.
Featured articles and news
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.






















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.