Schedule of condition of property
Contents |
[edit] Introduction
A schedule of condition (SOC) is a factual record of the condition of a property, normally prepared for legal or contractual reasons. Schedules of condition can be prepared for either residential or commercial buildings.
They create a complete record of the condition of the property on a particular date that can be used as a benchmark against which its condition can be assessed in the future and any changes identified.
Schedules of condition may be prepared under the instruction of a landlord, a tenant, an employer, a contractor, or a neighbour. Appointing an independent expert to prepare a schedule of condition should help to give it greater weight if there are subsequent claims or negotiations. It may be beneficial to seek agreement of the other party that the schedule is a fair reflection of the condition of the property when it is prepared.
It is important to recognise that identifying a change in the condition of a property does not necessarily attribute blame for that change.
[edit] Leases
For commercial or residential property leases, a schedule of condition can be required when a new lease is entered into to confirm the condition of the property. This ensures that the condition recorded so that any existing defects and their repair costs are identified prior to a commitment to lease being made, and can help with lease negotiation. It can also be used to establish responsibility for dilapidations and reinstatement, typically towards the end of a lease.
[edit] Construction
A schedule of conditions might be prepared before construction begins for adjacent properties or structures that will be retained, or if part of a building is being refurbished. This not only helps protect against potential claims from neighbours, who may only begin to notice pre-existing defects in their property when the noise and vibration of construction begins, but can also establish contractor liability for damage to the employer’s properties.
[edit] Party walls
For both commercial and residential properties, a schedule of condition can be prepared where the Party Wall etc. Act 1996 applies. This is to provide evidence of the condition of the neighbouring building prior to works beginning. The party wall surveyors can then undertake a re-inspection of the building and determine whether any damage has occurred and also what repairs should be carried out.
[edit] Contents
Typically, schedules of condition are prepared by surveyors and may comprise:
- The purpose of the schedule.
- Details of the location and extent of the property being assessed.
- A general description of the construction of the property.
- The time, date and weather conditions under which the inspection was made.
- Aspects of the property included in or excluded from the assessment.
- The purposes for which the schedule may be relied.
- Drawings of the property.
- Definitions (for example, ‘slight’, ‘moderate’ and ‘severe’).
- A written schedule setting out the location and nature of each item inspected (inside and out) and its condition and any other remarks. This will describe the overall condition and may identify existing issues, such as cracks, staining, holes, decay, discolouration, leaks and other defects, disrepair or deterioration
- Accompanying photographs and video.
- Specific tests that may have been carried out.
[edit] Related articles on Designing Buildings Wiki
- Betterment.
- Condition.
- Defects.
- Dilapidations.
- Homes (Fitness for Human Habitation) Act 2018.
- Mobilisation.
- Party wall act.
- Schedule.
- Schedule of defects.
- Schedule of dilapidations.
- Scott schedule.
- Supersession.
- Three party wall notice responses.
[edit] External references
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments