Prime cost in construction contracts
In general terms, the ‘prime cost’ is the sum of the direct cost of materials and labour associated with a production process. It is the direct cost of the inputs to a process that are necessary to create the output. If the prime cost can be lowered, the process may become more profitable.
In construction, the term ‘prime cost sum’ (PC sum) is an allowance for the supply of labour, plant and materials to be provided by a contractor or supplier that will be nominated by the client. The allowance is exclusive of any profit mark up or attendance (such as material handling, scaffolding and rubbish clearance etc) by the main contractor. See prime cost sum for more information.
Prime cost contracts (sometimes referred to as cost plus contracts or cost reimbursement contracts) are contracts in which the contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for profit and overheads.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete, for example for urgent alteration or repair work. See Prime cost contract for more information.
Adjustments may be permitted to prime costs during the period of a contract to allow for inflation (fluctuations).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.




















Comments
Construction on this page has been spelt incorrectly! - well spotted, this has been fixed