How long does planning permission last
Before 1968, there was no limit on the duration of planning permissions. Between 1968 and 2009, the duration of a permission was generally set out in the conditions to the permission, often limited to 5 years within which time construction had to begin, although it was sometimes possible to extend this by applying to vary the condition.
However, since 2009, unless the permission states otherwise, development should begin within 3 years of the date permission was granted.
The development is considered to have begun ‘…on the earliest date that a "material operation" in connection with the development is started’, that is:
- Any work of construction in the course of the erection of a building.
- Any work of demolition of a building.
- The digging of a trench which is to contain the foundations, or part of the foundations, of a building.
- The laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned (above).
- Any operation in the course of laying out or constructing a road or part of a road.
- Any change in the use of any land which constitutes material development.
Ref Town and Country Planning Act 1990, Section 56.
Lawfully commencing the development works may first involve satisfying conditions applied to the permission.
If the development has not commenced within three years, the permission will be considered to have expired, and if the applicant still wishes to proceed with the development, they will need to renew the application. Renewal is generally less onerous than making a fresh application, but a fee is payable. If however, the conditions under which the original permission was granted have changed, it may be necessary to make a fresh application.
Once the development has commenced, the permission remains in place unless the local authority serves a completion notice. If such a notice is served, the development must then be completed within 12 months.
If an outline planning application has been made, then the relevant reserved matters applications must be made within three years. The permission will then last for a further 2 years.
See also: How long does it take to get planning permission.
[edit] Related articles on Designing Buildings
- Approval of conditions on a planning permission.
- Avoiding planning permission pitfalls.
- Community Infrastructure Levy.
- Design and access statements.
- Detailed planning application.
- Environmental impact assessment.
- Extensions to time limits for implementing existing planning permissions.
- How long does it take to get planning permission.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning performance agreement.
- Planning permission.
- Pre-application advice.
- The difference between planning permission building regulations approval.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Listed structures on the rail network
Heritage interests and operational requirements must be balanced.
Historic England publishes research into embodied carbon when retrofitting traditional buildings.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.
Heritage and conservation science workforce survey - Have your say.
England's Suburbs 1820-2020. Book review.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.


















Comments