Three party wall notice responses
Contents |
[edit] Introduction
Whenever a Party Wall Notice is served by a building owner to an adjoining owner, the adjoining owner has 14 days from the notice date to formally respond. A notice is legally deemed as received “in the ordinary course of post”; therefore, the recommended allowance is a further two days or a total of 16 days.
The adjoining owner has three specific response choices when served a Party Wall Notice:
- Consent to the works.
- Dissent to the works and appoint an agreed surveyor.
- Dissent to the works and appoint their own Party Wall Surveyor.
[edit] Consent to works
This option means the building owner can proceed without any further surveying formalities or procedures being followed. It also preserves the securities the act affords an Adjoining Owner.
Consent preserves the Schedule of Condition (SOC) of Property Report which records the pre-construction condition of the adjoining owner’s property. This report is helpful if the works cause damage and proof is needed to show the damage was absent before the start of construction.
[edit] Dissent and appointment of an agreed surveyor
If the adjoining owner dissents to the works, an agreed surveyor can be appointed to act objectively on behalf of both parties. This option is often in the best interest of the building owner and can be more time and cost effective than using two surveyors. For instance, if damage occurs during development, an agreed surveyor will have all of the details associated with the pre-construction condition of the adjoining owner's property.
[edit] Dissent and appointment of respective surveyors
A dissenting adjoining owner can also appoint their own surveyor to work directly with the building owner's surveyor. This can result in cost implications.
[edit] Related articles on Designing Buildings
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.