JCT Design and Build Contract
The Joint Contracts Tribunal (JCT) Design and Build Contract (DB) is intended for use on construction projects following the design and build procurement route. This involves appointing a main contractor to design (or complete the design) of the project and then to go on and construct it. This is as opposed to the traditional procurement route in which the client appoints consultants to design the project and then a contractor is appointed to construct it.
Design and build gives a single point of responsibility for delivering the entire project, and can help ensure good buildability, cost control and speed. Some clients however, consider it is only appropriate for simple projects, where retaining control over the design is not the main priority.
The scale and complexity of design and build projects can vary considerably, but the DB contract is generally suitable for projects where a detailed agreement is required, making provision for collaborative working, sustainability, advance payment, third party rights, bonds, collateral warranties and so on.
The 2016 edition of the contract includes the following documents:
- Design and Build contract guide (DB/G).
- Design and Build sub-contract agreement (DBSub/A).
- Design and Build sub-contract conditions (DBSub/C).
- Short form of sub-contract (ShortSub): For small-scale subcontract works that are simple and involve low risk.
- Sub-subcontract (SubSub).
- Design and Build sub-contract guide (DBSub/G).
- Design and Build contract (DB) Tracked Change Document: Highlights the changes between the DB 2011 and 2016 editions.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Construction management contract.
- Design and build.
- Design and build - pros and cons.
- Intermediate building contract.
- JCT.
- JCT minor works building contract.
- JCT Sub-subcontract.
- Major project construction contract.
- Management Building Contract.
- Prime cost contract.
- Standard Building Contract.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.



















Comments
If the design build contractor is the actual designer and is responsible to procure the materials but not required to build. Can he change the material prices after signing the contract
What does the contract say - does it allow them to change prices? eg are fluctuations allowed?