Rag report
A RAG report (RAG rating, RAG status or Delivery Confidence Assessment) presents a status assessment using the traffic light colour designations; Red, Amber or Green. This gives a very visual and immediate way of identifying problem areas and potential problem areas.
The precise definition of different colour designations will vary between organisations, and so it is important that it is clearly set out, understood and used consistently. Typically, specific tasks, or components will be designated a colour status, where:
- Red indicates that primary objectives are at serious risk and remedial action is necessary.
- Amber indicates that it is possible the item will progress as planned but there is a problem and the objectives may be at risk. Action is being taken, or the problem is being monitored.
- Green indicates that the item is progressing as planned and that no action is necessary.
RAG reports can be used for a number of different purposes, including:
- Assessing the overall status of a project or portfolio of projects.
- Risk assessment.
- Assessing suppliers progress.
- Assessing resource capacity.
- Tracking third party dependencies.
- Post occupancy evaluations.
- Guiding designers about areas of the project requiring further development or change.
Individual Items may be assessed against a range of key performance indicators such as; programme, budget, compliance with the brief, sustainability, health and safety, energy performance and so on.
RAG reports are not an end in their own right, and are only effective if they are used as a way of instigating targeted action. Some organisations may adopt a reporting strategy that sets out who needs to be informed if an item is given an amber or red designation, and when items may need to be escalated.
RAG designations may need to be accompanied by additional information explaining the position, as ratings in isolation can be misleading or uninformative particularly in the early stages of projects, where red or amber designations may be given simply due to the level of development of the project and the inevitable uncertainty surrounding it. A red designation may not result in a failure as long as strategies are in place to move towards an amber and then green designation as the project progresses. Reports may include previous designations to give a sense of the direction of travel.
Some reports adopt an extended five-point traffic light system, including a green/amber and amber/red designation to give a finer degree of assessment, where:
- Amber/red indicates that there is serious doubt about whether the item will progress as planned and action is necessary.
- Green/amber indicates that the item is likely to progress as planned, but attention is necessary to ensure that risks do not develop into issues that might threaten the project objectives.
Blue is sometimes used to indicate that an item has been completed, or that responsibility has transferred to another organisation.
NB the OGC Gateway 3 Investment decision adopted by the Infrastructure and Projects Authority (IPA) is:
| RAG | Criteria Description |
| Green | Successful delivery of the project to time, cost and quality appears highly likely and there are no major outstanding issues that at this stage appear to threaten delivery. |
| Amber/Green | Successful delivery appears probable. However, constant attention will be needed to ensure risks do not materialise into major issues threatening delivery. |
| Amber | Successful delivery appears feasible but significant issues already exist requiring management attention. These appear resolvable at this stage and, if addressed promptly, should not present a cost/schedule overrun. |
| Amber/Red | Successful delivery of the project is in doubt with major risks or issues apparent in a number of key areas. Urgent action is needed to ensure these are addressed, and establish whether resolution is feasible. |
| Red | Successful delivery of the project appears to be unachievable. There are major issues which, at this stage, do not appear to be manageable or resolvable. The project may need re-base lining and/or overall viability re-assessed. |
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?