Rag report
A RAG report (RAG rating, RAG status or Delivery Confidence Assessment) presents a status assessment using the traffic light colour designations; Red, Amber or Green. This gives a very visual and immediate way of identifying problem areas and potential problem areas.
The precise definition of different colour designations will vary between organisations, and so it is important that it is clearly set out, understood and used consistently. Typically, specific tasks, or components will be designated a colour status, where:
- Red indicates that primary objectives are at serious risk and remedial action is necessary.
- Amber indicates that it is possible the item will progress as planned but there is a problem and the objectives may be at risk. Action is being taken, or the problem is being monitored.
- Green indicates that the item is progressing as planned and that no action is necessary.
RAG reports can be used for a number of different purposes, including:
- Assessing the overall status of a project or portfolio of projects.
- Risk assessment.
- Assessing suppliers progress.
- Assessing resource capacity.
- Tracking third party dependencies.
- Post occupancy evaluations.
- Guiding designers about areas of the project requiring further development or change.
Individual Items may be assessed against a range of key performance indicators such as; programme, budget, compliance with the brief, sustainability, health and safety, energy performance and so on.
RAG reports are not an end in their own right, and are only effective if they are used as a way of instigating targeted action. Some organisations may adopt a reporting strategy that sets out who needs to be informed if an item is given an amber or red designation, and when items may need to be escalated.
RAG designations may need to be accompanied by additional information explaining the position, as ratings in isolation can be misleading or uninformative particularly in the early stages of projects, where red or amber designations may be given simply due to the level of development of the project and the inevitable uncertainty surrounding it. A red designation may not result in a failure as long as strategies are in place to move towards an amber and then green designation as the project progresses. Reports may include previous designations to give a sense of the direction of travel.
Some reports adopt an extended five-point traffic light system, including a green/amber and amber/red designation to give a finer degree of assessment, where:
- Amber/red indicates that there is serious doubt about whether the item will progress as planned and action is necessary.
- Green/amber indicates that the item is likely to progress as planned, but attention is necessary to ensure that risks do not develop into issues that might threaten the project objectives.
Blue is sometimes used to indicate that an item has been completed, or that responsibility has transferred to another organisation.
NB the OGC Gateway 3 Investment decision adopted by the Infrastructure and Projects Authority (IPA) is:
| RAG | Criteria Description |
| Green | Successful delivery of the project to time, cost and quality appears highly likely and there are no major outstanding issues that at this stage appear to threaten delivery. |
| Amber/Green | Successful delivery appears probable. However, constant attention will be needed to ensure risks do not materialise into major issues threatening delivery. |
| Amber | Successful delivery appears feasible but significant issues already exist requiring management attention. These appear resolvable at this stage and, if addressed promptly, should not present a cost/schedule overrun. |
| Amber/Red | Successful delivery of the project is in doubt with major risks or issues apparent in a number of key areas. Urgent action is needed to ensure these are addressed, and establish whether resolution is feasible. |
| Red | Successful delivery of the project appears to be unachievable. There are major issues which, at this stage, do not appear to be manageable or resolvable. The project may need re-base lining and/or overall viability re-assessed. |
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.