Production information report for design and construction
The production information report is a work stage report produced by the consultant team for the client at the end of the production information stage (see free work plans on the Designing Buildings Wiki home page).
It is the last opportunity for the client to consider issues to do with the design of the development and the form of contract before the tender process begins. It may also be the first time that the client has seen drawings describing key components (such as door handles), assemblies and specialist items. As a result, the client may wish to issue the production information report (or parts of it) for consideration to key users (or user panels) and perhaps to their lawyer or other independent client advisers. Once the main contractor has been appointed, subsequent changes can become very expensive.
The production information report may include:
- The approximate quantities cost plan and cash flow projection.
- Packaging strategy (and costs associated with individual packages).
- An assessment of cost uncertainty and the reasons for this.
- Identification of provisional sums.
- A schedule of outstanding information (including any client contributions that will be required for the contract documents).
- A schedule of outstanding consents (such as statutory approvals or planning conditions).
- A description of proposed preliminaries and other items to bring to the client's attention.
- Proposed warranties and bonds.
- The proposed form of contract, contract conditions and any proposed changes to the contract.
- Proposed treatment of liquidated damages.
- A schedule of exclusions from the contract.
- Any insurance issues.
- Drawings and specifications describing key components, assemblies and specialist items.
- A list of any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
- An assessment of the possible use of preliminary contracts.
- An assessment of the possibility of ordering long-lead items early.
- The proposed date of possession.
- Tender procedures and the tender period.
- An assessment of the need to appoint site inspectors.
- An assessment of the need to appoint party wall surveyor(s).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Sustainable urban drainage systems SUDS
Rooflights, skylights, roof windows and Part L
Shedding some light on the new Building Regulations.
Interview with historic built environment surveyor.
Upgraded membership category now requires assessment.
The average kinetic energy of molecules
Temperature in buildings, explained on DB
Women and unequal pay in project management
Main barrier to entering the profession, new study reveals.
IHBC’s response to Parliamentary Committee
On Levelling-Up and Regeneration Bill.
Finalists for 2022 CIOB Awards revealed
Over 70 managers and organisations shortlisted for the 14 awards.
Types of building sensors on BD
From biometric to electrical current, chemical and more.
Government mandates detectors in rented homes
Changes are due to come into force on 1st October 2022.
80% of major government projects are rated red or amber
Heed advice and insight of this report IPA tells the government.
The end of the games but continued calls for action
From the Commonwealth Association of Architects.
Sustainable urban drainage systems SUDS
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.