Procurement Route Pros & Cons
Contents |
[edit] Traditional Procurement
Good for:
- QUALITY – full design pre tender
- DESIGN FLEXIBILITY – variations & instructions
- SPECIALIST SUB-CON’S – Named specialist update sbc11
- DESIGN CONTROL – through arch/CA
- CDPs – eg. M&E
- COMPLEX
- COST – lump sum cost benefits unless multiple changes made
Not Suited for:
- TIME – req full detailed pack pre tender
- COST – not a benefit if many changes made
- INCOMPLETE DRAWINGS – lead to delay, costs and claims of negligence
Contract: SBC11
- LUMP SUM PAYMENT
- CDM
- CDP’s
- NAMED SUB CONTRACTORS
- VARIATIONS/INSTRUCTIONS
- RETENTION
- COLLATERAL WARRANTIES
- TERMINATION PROVISIONS
- PREAGREED ALT DISPUTE RESOLUTION
[edit] D&B Procurement
Good for:
- TIME – Fast track, overlap design & construction
- COST – lump sum/ GMP
- SINGLE POINT RESPONSIBILITY – Contractor design and build responsibility
- COMPLEX
- NOVATION – can benefit quality. Prior knowledge, sub-con drawing review
- CLIENT RISK LOW
- NAMED SUB-CON – in employers requirements
Not suited for:
- QUALITY – cheapest route to meet contract spec can lead to low quality products/ build quality.
- DESIGN FLEXIBILITY – request for change – costs/time implications
Contract: DB11
- CONTRACTOR TO COMPLETE DESIGN +CARRY OUT WORKS
- LUMP SUM/GMP
- CDM
- COLLATERAL WARRANTIES
- TERMINATION PROVISIONS
- RETENTION
- PRE AGREED DISPUTE RESOLUTION
[edit] Management Contracting Procurement
Good for:
- COMPLEX/SPECIALIST – individually appointed packages to best suited sub-contractor
- POTENTIAL COST SAVING – Competitive tender
- TIME – Overlap design/construction
- QUALITY – each package subcontracted to specialist
- DESIGN FLEXIBILITY – changes can be made throughout construction. Potential costs.
Not suited for:
- INEXPERIENCED – risk high
- FIXED COST - Prime cost basis per package. Fluctuations.
- LACK OF AVAILABLE SPECIALISTS – would leave gaps in work to be undertaken.
Contract: MC11
- PRIME COST CONTRACT
- PROVISIONS FOR COLLATERAL WARRANTIES
- SUSTAINABILITY
- COLLABERATIVE WORKING
- THIRD PARTY RIGHTS – funder-contractor
[edit] Construction Management Procurement
Good for:
- COMPLEX/SPECIALIST - individually appointed packages to best suited sub-contractor
- TIME - Overlap design/construction
- DESIGN FLEXIBILITY - changes can be made throughout construction. Potential costs.
- POTENTIAL COST SAVING - Competitive tender
- QUALITY - each package subcontracted to specialist
- ALL BUILDING TYPES
- EFFICIENCY – Early appointment of CM to aid programme
Not suited for:
- UNEXPERIENCED EMPLOYER – risk high as appointing trade contractors
- FIXED COST- Prime cost basis per package.
- LACK OF AVAILABLE SPECIALISTS
Contracts:
CM/TC11
CM/A
- EMPLYER – CM
- COLLATERAL WARRANTIES
- SUSTAINABILITY
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Dorset's first conservation campaigner?
Gov.uk - Hot-rolled steel plate
New anti-dumping measure imposed on South Korea.
ECA responds to the Milburn Report
Youth employment to be linked to workforce demand.
The construction industry urgently needs to attract new talent
CIOB responds to Neets report.
Grenfell Tower community update
Memorial columns to be retained as careful dismantling continues.
When buildings reflected the local resources available.
CIOB reports 57% are using artificial intelligence technologies.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.