Parkwood Leisure Limited v Laing
Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited [2013] EWHC 2665 (TCC)
About the time the Housing Grants Construction and Regeneration Act 1996 (“the Act”) was passed, I recall asking my training principal whether a collateral warranty constituted a construction contract for the purposes of the Act. “Interesting question” came the response. Here’s an interesting answer................
Contents |
Background
Laing O’Rourke (“Laing”) the defendant Contractor was engaged under a standard JCT design and build contract to carry out and complete the design and construction of a swimming and leisure facility for Orion Land and Leisure (Cardiff) Ltd, (“Orion”), the employer. Orion granted a lease to Parkwood Leisure Ltd (“Parkwood”), the claimant, a facilities management company who operated the pool for them.
The building contract contained a term requiring Laing to provide collateral warranties to a number of third parties, among them, Parkwood. Before the works were completed, Laing executed a collateral warranty in favour of Parkwood.
A number of problems arose after the pool was open with Parkwood alleging construction and commissioning defects, mainly defects with the air handling units.
Some of these problems were settled under a settlement agreement made between Parkwood and Laing, however issues with the air handling units persisted so Parkwood sought to claim against Laing under its collateral warranty.
Parkwood brought (CPR Part 8) proceedings for a determination as to whether:
- The collateral warranty amounted to a construction contract for the purposes of the Housing Grants Construction and Regeneration Act which would then enable it to adjudicate its claim.
- The present claim was compromised in the settlement agreement.
The collateral warranty
The collateral warranty contained the following clause: “The Contractor warrants, acknowledges and undertakes that [emphasis added]:-
- 1. It has carried out and shall carry out and complete the Works in accordance with the Contract;
- 3. In the design of Works.....the Contractor...has exercised and will continue to exercise all reasonable skill and care to be expected of an architect......;
- 7. It has complied and will continue to comply with the terms of regularly and diligently carry out its obligations under the Contract.”
The judge, Mr Justice Akenhead, then looked at the definition of “construction contract” and “construction operations” under sections 104 and 105 of the Act and decided that Parkwood’s collateral warranty was a construction contract as the definitions were widely construed and the Act applies to all contracts related to the carrying out of construction operations. The warranty was subsidiary to the building contract which was itself a construction contract. The judge noted wording in the warranty relating expressly to the carrying out and completing of the works, i.e., a prospective obligation to finish the remaining works.
Not all collateral warranties will be construed as construction contracts for the purposes of the Act; that, of course, depends on the wording of the warranty. The judge indicated that warranties which relate to future performance might be considered construction contracts whereas a pointer against may be that all the works are completed with the Contractor warranting the works after completion.
Parkwood therefore succeeded in obtaining a declaration that its collateral warranty amounted to a construction contract for the purposes of the Act thereby opening the door to adjudication.
The settlement agreement
Whilst certain matters relating to the air handling units were settled between the parties in the settlement agreement there was scope to bring claims which did not exist at the date of the agreement. The lesson to be learned here is the old nugget of clear and careful drafting and avoiding ambiguities that can come back to bite by reopening matters previously considered closed.
Conclusion
The court’s decision is an unexpected one for practitioners who assumed the Act did not apply to warranties.
Collateral warranties will now be subject to greater scrutiny in the light of this case. We may now see a resistance among contractors and consultants to grant warranties and a desire to perhaps restrict the number and scope of warranties so that their application is limited to be retrospective only. That inevitably means further complications for the negotiation and drafting of warranties resulting in protracted and costly negotiations.
The decision also raises speculation as to the application of the Act’s Scheme for Construction Contracts and payment provisions to warranties considered to be construction contracts.
The upshot of this could now see the rise of third party rights as circumventing the issues arising from this case. Could this spell the end of the widespread use of warranties which may finally be falling out of favour?
This article was created by construction lawyer --Najma Dunnett as part of an ongoing series of legal articles. Follow Najma on Twitter to keep up to date with the latest changes in construction law @NDunnett_Cons.
Find out more
Related articles on Designing Buildings Wiki
- Adjudication.
- Collateral warranties.
- Construction contract.
- Defects.
- Definition of collateral warranty.
- Housing Grants Construction and Regeneration Act.
- Reasonable skill and care.
- Scheme for Construction Contracts.
- Third party rights.
External references
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.























Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.