Northern Ireland’s Central Procurement Directorate issues standard Z clauses for the NEC3
The Central Procurement Directive (CPD) in Northern Ireland has standardised the use of NEC Z clauses for central government construction work in Northern Ireland. The Guidance Note is an extremely valuable resource and is a model of how Z clauses should be incorporated.
Procurement Guidance Note 01/15 dated 8 May 2015 is an excellent example of how Z clauses for the NEC should be incorporated. Z clauses are frequently used to improperly transfer risk or to totally (if unintentionally) confuse the use of the NEC form of contract. However, they are not without merit. With the support of the NEC Users Group and the construction industry parties that engage with them in Northern Ireland, CPD has done a remarkable job of making the process of drafting Z clauses easier.
The Guidance Note is not copyrighted and offers a model for how others can and should adopt Z clauses. It includes a section for 28 typical Z clauses. The Note describes the “purpose” of each clause and gives some guidance as to how it is to be adopted. Some of the clauses are compulsory (for those subject to the Northern Ireland Procurement Policy) and others discretionary.
The Z clauses include many * that are relatively non-contentious and it goes some way to dealing with tricky issues such as two stage contracting (where there is a design which must be accepted before build commences) and the incorporation of a contractor’s quality submissions into the contractual framework.
However, it is arguable that further clarity could have been provided. The document could have:
- Clarified Secondary Option W2 on dispute resolution to make sure that it aligns with the law on adjudication; and
- Removed any ambiguity around the definition of a defect when the problem is the contractors’ service and/or their failure to comply with constraints rather than the actual work done.
Discretionary amendments to the compensation clauses are extremely light touch. There is no standardised amendment to the often changed Clause 19 and the only substantive change to the compensation event system is to move the risk of unforeseen physical conditions in 60.1(12) to the contractor in certain, tightly-defined circumstances.
On the positive side, the control of subcontractors, particularly in relation to those nominated by a contractor in a tendering process, is tightened up and the employer is given an express right to terminate for contraventions of bribery, fraud and the like – although this last point is prefaced as being optional which may cause the employer some difficulties. The “purpose” element of each Z clause, with the corresponding descriptions of intention, could be tightened up to make it clearer when a public authority should use the clauses but there can be absolutely no doubt this is a massive step forward for all in the industry.
The guidance note is essential reading for all NEC3 practitioners and procurers alike.
--Quigg Golden 09:37, 6 July 2015 (BST)
Featured articles and news
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”























