Northern Ireland’s Central Procurement Directorate issues standard Z clauses for the NEC3
The Central Procurement Directive (CPD) in Northern Ireland has standardised the use of NEC Z clauses for central government construction work in Northern Ireland. The Guidance Note is an extremely valuable resource and is a model of how Z clauses should be incorporated.
Procurement Guidance Note 01/15 dated 8 May 2015 is an excellent example of how Z clauses for the NEC should be incorporated. Z clauses are frequently used to improperly transfer risk or to totally (if unintentionally) confuse the use of the NEC form of contract. However, they are not without merit. With the support of the NEC Users Group and the construction industry parties that engage with them in Northern Ireland, CPD has done a remarkable job of making the process of drafting Z clauses easier.
The Guidance Note is not copyrighted and offers a model for how others can and should adopt Z clauses. It includes a section for 28 typical Z clauses. The Note describes the “purpose” of each clause and gives some guidance as to how it is to be adopted. Some of the clauses are compulsory (for those subject to the Northern Ireland Procurement Policy) and others discretionary.
The Z clauses include many * that are relatively non-contentious and it goes some way to dealing with tricky issues such as two stage contracting (where there is a design which must be accepted before build commences) and the incorporation of a contractor’s quality submissions into the contractual framework.
However, it is arguable that further clarity could have been provided. The document could have:
- Clarified Secondary Option W2 on dispute resolution to make sure that it aligns with the law on adjudication; and
- Removed any ambiguity around the definition of a defect when the problem is the contractors’ service and/or their failure to comply with constraints rather than the actual work done.
Discretionary amendments to the compensation clauses are extremely light touch. There is no standardised amendment to the often changed Clause 19 and the only substantive change to the compensation event system is to move the risk of unforeseen physical conditions in 60.1(12) to the contractor in certain, tightly-defined circumstances.
On the positive side, the control of subcontractors, particularly in relation to those nominated by a contractor in a tendering process, is tightened up and the employer is given an express right to terminate for contraventions of bribery, fraud and the like – although this last point is prefaced as being optional which may cause the employer some difficulties. The “purpose” element of each Z clause, with the corresponding descriptions of intention, could be tightened up to make it clearer when a public authority should use the clauses but there can be absolutely no doubt this is a massive step forward for all in the industry.
The guidance note is essential reading for all NEC3 practitioners and procurers alike.
--Quigg Golden 09:37, 6 July 2015 (BST)
Featured articles and news
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.