Modular vs traditional construction
This article provides an outline of the important differences between modular and traditional construction methods:
- The term ‘traditional’ is often used to describe the types of linear construction, where each individual step is not only constructed entirely (or largely) on site, but also needs to be completed before the project can move on to the next phase.
- Modular construction is an off-site based construction method, during which individual components are manufactured (or ‘prefabricated’) in a factory, transported to the site entirely (or mostly) complete and assembled on location.
Both construction methods start in the same way – planning, design, approvals, site preparation and development. From that point forward, however, the differences begin:
Image source: Modscape
Pros and Cons of Modular Construction
Pros:
- Thanks to the ability for the project to run simultaneously on-site and in-factory, modular construction can be up to 50% quicker than traditional construction.
- As major parts of construction are handled within a factory, weather conditions are often irrelevant during the majority of the project.
- The factory-based manufacturing process allows not only for greater quality control during the manufacturing process but for many health and safety risks to be considerably reduced, if not eliminated,
- The process aims to minimise waste and reduce the project’s carbon footprint, as fewer people are travelling to the site and modules are produced directly to spec using Computer Aided Manufacturing.
- The impact on the community surrounding the construction site can be significantly reduced, due to much lower levels of noise and traffic during the project period
- The methods employed in modular construction can often benefit the energy efficiency and airtightness of the final construction
Cons:
- Access to the site must be considered from the very beginning, as it will need to allow for the delivery of large modules.
- Traditional construction allows for later design changes, while modular construction is unlikely to be able to factor these in, so early complete design sign off is crucial with clients.
- The logistics and planning of individual module assembly will need rigorous planning to ensure a smooth project.
Ultimately, each project should be considered individually. The method that is selected should match the ultimate desired outcome and the individual limitations of each project.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.



















Comments