Modular classrooms: The Friars Primary School extension
Contents |
[edit] Introduction
The Friars Primary School modular classroom extension was a project undertaken in 2016. Friars Primary School is in Salford, Manchester. The school leadership identified the need for a new, bespoke modular educational facility.
[edit] Project requirements
The school was experiencing rapid growth in student population. There was a boom in primary school numbers that put pressure on many educational establishments.
The contract was awarded in April. The onsite work began in May, and the modular building was delivered in July. With the fit-out completed over the summer, the new facility was available at the start of the next school year.
The size of the project and the timeline were ambitious. The six-bay modular building was constructed on the playing fields at the front of the current site. The facilities needed to be available for the new school year, with limited disruption to the ongoing learning taking place on-site.
[edit] Finding solutions
Designers communicated with education leaders and presented a single-storey facility. The modular building offered the required classrooms and other facilities.
Each classroom was installed with roof lights, which provided the teacher with smart control. These controlled roof lights were also linked to carbon dioxide and rain sensors.
Natural light is essential to wellbeing and to improved learning outcomes. Artificial light can make learning challenging. Therefore, the fan lights that were fitted above the doors enhanced the natural light in the classroom.
The goal was to live up to the eco-friendly ambitions of the school by making the environment as natural as possible. LED lighting was used throughout with PIR detection. Air leakage was also kept low so the building will retain heat. Lower heating costs also mean more school budget for essential resources for learning.
Equally important is the aesthetic of the building. This is an extension to an existing school. Therefore, the school needed the opportunity to select the colours and finishes for the new classroom building and match these to the existing structure. The new extension was at the front of the school and was going to be prominent on the site.
[edit] Summary
There was little chance that a traditional bricks and mortar construction project could have been complete in time to meet the deadline. The project was completed and presented to the client in 10 weeks. Such was the efficiency of the project; the school was able to work well as the extension was being delivered.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.