[edit] Introduction
The Friars Primary School modular classroom extension was a project undertaken in 2016. Friars Primary School is in Salford, Manchester. The school leadership identified the need for a new, bespoke modular educational facility.
[edit] Project requirements
The school was experiencing rapid growth in student population. There was a boom in primary school numbers that put pressure on many educational establishments.
The contract was awarded in April. The onsite work began in May, and the modular building was delivered in July. With the fit-out completed over the summer, the new facility was available at the start of the next school year.
The size of the project and the timeline were ambitious. The six-bay modular building was constructed on the playing fields at the front of the current site. The facilities needed to be available for the new school year, with limited disruption to the ongoing learning taking place on-site.
[edit] Finding solutions
Designers communicated with education leaders and presented a single-storey facility. The modular building offered the required classrooms and other facilities.
Each classroom was installed with roof lights, which provided the teacher with smart control. These controlled roof lights were also linked to carbon dioxide and rain sensors.
Natural light is essential to wellbeing and to improved learning outcomes. Artificial light can make learning challenging. Therefore, the fan lights that were fitted above the doors enhanced the natural light in the classroom.
The goal was to live up to the eco-friendly ambitions of the school by making the environment as natural as possible. LED lighting was used throughout with PIR detection. Air leakage was also kept low so the building will retain heat. Lower heating costs also mean more school budget for essential resources for learning.
Equally important is the aesthetic of the building. This is an extension to an existing school. Therefore, the school needed the opportunity to select the colours and finishes for the new classroom building and match these to the existing structure. The new extension was at the front of the school and was going to be prominent on the site.
[edit] Summary
There was little chance that a traditional bricks and mortar construction project could have been complete in time to meet the deadline. The project was completed and presented to the client in 10 weeks. Such was the efficiency of the project; the school was able to work well as the extension was being delivered.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.