Modular classrooms: The Friars Primary School extension
Contents |
[edit] Introduction
The Friars Primary School modular classroom extension was a project undertaken in 2016. Friars Primary School is in Salford, Manchester. The school leadership identified the need for a new, bespoke modular educational facility.
[edit] Project requirements
The school was experiencing rapid growth in student population. There was a boom in primary school numbers that put pressure on many educational establishments.
The contract was awarded in April. The onsite work began in May, and the modular building was delivered in July. With the fit-out completed over the summer, the new facility was available at the start of the next school year.
The size of the project and the timeline were ambitious. The six-bay modular building was constructed on the playing fields at the front of the current site. The facilities needed to be available for the new school year, with limited disruption to the ongoing learning taking place on-site.
[edit] Finding solutions
Designers communicated with education leaders and presented a single-storey facility. The modular building offered the required classrooms and other facilities.
Each classroom was installed with roof lights, which provided the teacher with smart control. These controlled roof lights were also linked to carbon dioxide and rain sensors.
Natural light is essential to wellbeing and to improved learning outcomes. Artificial light can make learning challenging. Therefore, the fan lights that were fitted above the doors enhanced the natural light in the classroom.
The goal was to live up to the eco-friendly ambitions of the school by making the environment as natural as possible. LED lighting was used throughout with PIR detection. Air leakage was also kept low so the building will retain heat. Lower heating costs also mean more school budget for essential resources for learning.
Equally important is the aesthetic of the building. This is an extension to an existing school. Therefore, the school needed the opportunity to select the colours and finishes for the new classroom building and match these to the existing structure. The new extension was at the front of the school and was going to be prominent on the site.
[edit] Summary
There was little chance that a traditional bricks and mortar construction project could have been complete in time to meet the deadline. The project was completed and presented to the client in 10 weeks. Such was the efficiency of the project; the school was able to work well as the extension was being delivered.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.