Modular classrooms: The Friars Primary School extension
Contents |
[edit] Introduction
The Friars Primary School modular classroom extension was a project undertaken in 2016. Friars Primary School is in Salford, Manchester. The school leadership identified the need for a new, bespoke modular educational facility.
[edit] Project requirements
The school was experiencing rapid growth in student population. There was a boom in primary school numbers that put pressure on many educational establishments.
The contract was awarded in April. The onsite work began in May, and the modular building was delivered in July. With the fit-out completed over the summer, the new facility was available at the start of the next school year.
The size of the project and the timeline were ambitious. The six-bay modular building was constructed on the playing fields at the front of the current site. The facilities needed to be available for the new school year, with limited disruption to the ongoing learning taking place on-site.
[edit] Finding solutions
Designers communicated with education leaders and presented a single-storey facility. The modular building offered the required classrooms and other facilities.
Each classroom was installed with roof lights, which provided the teacher with smart control. These controlled roof lights were also linked to carbon dioxide and rain sensors.
Natural light is essential to wellbeing and to improved learning outcomes. Artificial light can make learning challenging. Therefore, the fan lights that were fitted above the doors enhanced the natural light in the classroom.
The goal was to live up to the eco-friendly ambitions of the school by making the environment as natural as possible. LED lighting was used throughout with PIR detection. Air leakage was also kept low so the building will retain heat. Lower heating costs also mean more school budget for essential resources for learning.
Equally important is the aesthetic of the building. This is an extension to an existing school. Therefore, the school needed the opportunity to select the colours and finishes for the new classroom building and match these to the existing structure. The new extension was at the front of the school and was going to be prominent on the site.
[edit] Summary
There was little chance that a traditional bricks and mortar construction project could have been complete in time to meet the deadline. The project was completed and presented to the client in 10 weeks. Such was the efficiency of the project; the school was able to work well as the extension was being delivered.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.