Low Value Disputes Model Adjudication Procedure LVD MAP
CIC Low Value Disputes Model Adjudication Procedure (CIC LVD MAP) and the CIC LVD MAP sets out a streamlined adjudication procedure for Low Value Disputes, and, by linking the Adjudicator’s fee to the amount claimed, provides certainty as to how much the Adjudicator will be paid for making an Adjudicator’s Decision. By including an outline timetable for the procedural stages it provides a flexible yet simple to understand approach to the key elements of the adjudication process.
The CIC LVD MAP can be adopted if the Parties have incorporated it into the Contract by reference, the reference shall be deemed to be to the edition current at the date of the Notice of Adjudication, unless expressly stated otherwise in the Contract. Alternatively, the Parties may agree to use the procedure on an ad-hoc basis when a dispute arises.
The existing CIC MAP Edition 5 (CIC LVD MAP) was approved by the CIC Business Panel in November 2019 and published on 1 May 2020, in light of the amendments to the Construction Act 1996. The CIC LVD MAP has been embraced by the UK construction industry, with about 800 adjudicator appointments from 1 May 2020 to the end of March 2025.
The MAP is a contractual adjudication procedure compliant with the Housing Grants, Construction and Regeneration Act 1996 incorporating the amendments made by the Local Democracy, Economic Development and Construction Act 2009. The procedure can be incorporated by reference into a contract or used by agreement of the parties; it is accompanied by a model adjudication agreement.
The amendments to the Construction Act came into effect on 1 October 2011 in England and Wales (1 November 2011 in Scotland) and affect everyone in business involved in construction work. All construction contracts which are entered into on or after 1 October 2011 must comply with the provisions of the amended Construction Act. In practical terms this will mean that all projects currently at the tender stage will be subject to the new provisions.
The new 5th edition of the Model Adjudication Procedure is available to purchase via the CIC Online Shop.
[edit] Related articles on Designing Buildings
- Adjudicator.
- Adjudicator Nominating Body ANB.
- Adjudication.
- Adjudicators and bias.
- Alternative dispute resolution.
- Alternative Dispute Resolution legislation.
- Arbitration.
- Arbitration v Adjudication.
- Breach of contract.
- Causes of construction disputes.
- Conciliation
- Contract claims.
- Contract conditions.
- Dispute resolution.
- Dispute resolution board.
- Expert determination.
- How does arbitration work?
- Joinder.
- Low Value Disputes Adjudication.
- Low Value Disputes Model Adjudication Procedure.
- Low Value Disputes Procedure LVDP.
- Mediation.
- Pay now argue later.
- Pendulum arbitration.
- PFIs and adjudication.
- The Housing Grants, Construction and Regeneration Act.
- The role of the mediator.
- The Scheme for Construction Contracts.
[edit] External Links
https://www.cic.org.uk/services/adjudication/cic-low-value-disputes-adjudication
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.