Pay now argue later
Construction Law Barrister Robert Fenwick Elliott coined the expression ‘Pay now, argue later’ to describe the adjudication process in early 1996 during discussions with Lord Howie of Troon in the tea room at the House of Lords. He describes below how this came about.
Lord Howie was a Scottish engineer, picking up the recommendation in Sir Michael Latham’s Report ‘Constructing the team’ to introduce an adjudication scheme into construction contracts, and very sensibly sought the input of TeCSA (Technology and Construction Solicitors’ Association) as to how this might best be done.
I was advising him to stay clear of his initial idea of making the adjudicator’s decision final and binding, on the basis that if it was final and binding, it would be impossible to prevent the courts from placing all sorts of obstacles in the way of enforcement. It was a play on the old hire purchase slogan: 'Buy now, pay later'. I said that if an adjudication loser was obliged to pay up, without prejudice to its right to then fight it out in the courts or arbitration to try to get it back, that would achieve the objective we were looking for, but minimising the risk of court interference. It would be rare, I predicted, that this right to 'argue later' would be used very much in practice. Happily, he agreed, and my prediction eventually proved good.
Lord Howie mentioned the formulation in debate on 28th March 1996, as did Lord Akner on 22nd April 1996.
It was picked up by the courts in the UK in Homer Burgess Ltd v Chirex (Annan) Ltd [1999 ScotCS 264 (10 November 1999)] and then in Australia in Multiplex Constructions Pty Ltd v Luikens and Anor [2003 NSWSC 1140 (4 December 2003).
Since then it has been used many times to characterise the nature of the adjudication process.
This article originally appeared at Pay now, Argue Later 15/01/2016.
It was written by --Robert Fenwick Elliott.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Alternative dispute resolution.
- Arbitration Act.
- Arbitration.
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Contract claims.
- Dispute resolution boards.
- Mediation.
- Pendulum arbitration
- Seven day letter
- The Housing Grants, Construction and Regeneration Act.
- The Scheme for Construction Contracts.
Featured articles and news
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.