Pay now argue later
Construction Law Barrister Robert Fenwick Elliott coined the expression ‘Pay now, argue later’ to describe the adjudication process in early 1996 during discussions with Lord Howie of Troon in the tea room at the House of Lords. He describes below how this came about.
Lord Howie was a Scottish engineer, picking up the recommendation in Sir Michael Latham’s Report ‘Constructing the team’ to introduce an adjudication scheme into construction contracts, and very sensibly sought the input of TeCSA (Technology and Construction Solicitors’ Association) as to how this might best be done.
I was advising him to stay clear of his initial idea of making the adjudicator’s decision final and binding, on the basis that if it was final and binding, it would be impossible to prevent the courts from placing all sorts of obstacles in the way of enforcement. It was a play on the old hire purchase slogan: 'Buy now, pay later'. I said that if an adjudication loser was obliged to pay up, without prejudice to its right to then fight it out in the courts or arbitration to try to get it back, that would achieve the objective we were looking for, but minimising the risk of court interference. It would be rare, I predicted, that this right to 'argue later' would be used very much in practice. Happily, he agreed, and my prediction eventually proved good.
Lord Howie mentioned the formulation in debate on 28th March 1996, as did Lord Akner on 22nd April 1996.
It was picked up by the courts in the UK in Homer Burgess Ltd v Chirex (Annan) Ltd [1999 ScotCS 264 (10 November 1999)] and then in Australia in Multiplex Constructions Pty Ltd v Luikens and Anor [2003 NSWSC 1140 (4 December 2003).
Since then it has been used many times to characterise the nature of the adjudication process.
This article originally appeared at Pay now, Argue Later 15/01/2016.
It was written by --Robert Fenwick Elliott.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Alternative dispute resolution.
- Arbitration Act.
- Arbitration.
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Contract claims.
- Dispute resolution boards.
- Mediation.
- Pendulum arbitration
- Seven day letter
- The Housing Grants, Construction and Regeneration Act.
- The Scheme for Construction Contracts.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.