Pay now argue later
Construction Law Barrister Robert Fenwick Elliott coined the expression ‘Pay now, argue later’ to describe the adjudication process in early 1996 during discussions with Lord Howie of Troon in the tea room at the House of Lords. He describes below how this came about.
Lord Howie was a Scottish engineer, picking up the recommendation in Sir Michael Latham’s Report ‘Constructing the team’ to introduce an adjudication scheme into construction contracts, and very sensibly sought the input of TeCSA (Technology and Construction Solicitors’ Association) as to how this might best be done.
I was advising him to stay clear of his initial idea of making the adjudicator’s decision final and binding, on the basis that if it was final and binding, it would be impossible to prevent the courts from placing all sorts of obstacles in the way of enforcement. It was a play on the old hire purchase slogan: 'Buy now, pay later'. I said that if an adjudication loser was obliged to pay up, without prejudice to its right to then fight it out in the courts or arbitration to try to get it back, that would achieve the objective we were looking for, but minimising the risk of court interference. It would be rare, I predicted, that this right to 'argue later' would be used very much in practice. Happily, he agreed, and my prediction eventually proved good.
Lord Howie mentioned the formulation in debate on 28th March 1996, as did Lord Akner on 22nd April 1996.
It was picked up by the courts in the UK in Homer Burgess Ltd v Chirex (Annan) Ltd [1999 ScotCS 264 (10 November 1999)] and then in Australia in Multiplex Constructions Pty Ltd v Luikens and Anor [2003 NSWSC 1140 (4 December 2003).
Since then it has been used many times to characterise the nature of the adjudication process.
This article originally appeared at Pay now, Argue Later 15/01/2016.
It was written by --Robert Fenwick Elliott.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Alternative dispute resolution.
- Arbitration Act.
- Arbitration.
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Contract claims.
- Dispute resolution boards.
- Mediation.
- Pendulum arbitration
- Seven day letter
- The Housing Grants, Construction and Regeneration Act.
- The Scheme for Construction Contracts.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.

















