Drawdown
Contents |
[edit] Introduction
In relation to property development finance, the term 'drawdown' can have numerous meanings, including a portion of the funding - or drawdown - received incrementally over the duration of the project. Under this definition, a drawdown on financing (such as a loan) may be taken in stages to finance a project. The incremental distribution of funds is sometimes referred to as a progressive drawdown.
In some instances, drawdown may refer to the initiation of a transaction - or drawdown - under a loan agreement. Under this definition, funds can become available (or are officially borrowed) on a drawdown date. It can also be an amount of money - or drawdown - borrowed for a specific purpose. This usage is considered informal and is not traditionally used in the context of property development financing.
When not associated with financial matters, drawdown may refer to the controlled reduction of fluids or pressure wells, reservoirs and so on.
[edit] Drawdown and cash flow
The incremental distribution of funds is sometimes referred to as a progressive drawdown. While a progressive drawdown provides resources as needed, the success of this approach may require careful planning to ensure cash is distributed at the appropriate stages based on the progress of the project.
If drawdown is dictated by a schedule provided by the funder, this may present issues during times when increased spending is necessary, but money is not available. There may also be periods when less money is required, and an unsuitable drawdown schedule will result in the unnecessary release of funding.
With a progressive drawdown, it is possible to lower interest payments when compared to situations where the entire amount is borrowed at the start of the project. However, if too much of a progressive drawdown is taken too quickly, this can result in the accrual of additional interest.
The agreed interest rate and drawdown facilities should be provided in the funding or loan contract. Interest rates might be fixed, variable and/or capped. Drawdown facilities (often on a quarterly basis) need to be more than sufficient and timed to meet monthly valuations. Often developers will base residual value calculations on drawing down all construction and professional payments by the two thirds stage of the project to avoid any risk of defaulting on payments.
Careful planning cannot always anticipate emergency situations that may have an impact on the progress of a project and the allocation of resources. In these instances, drawdown contingency management measures should be considered. One consideration may be the creation of a contingency drawdown curve which can be updated regularly for revised forecasting.
[edit] Drawdown requirements
There is some general information that is typically part of financing arrangements that have drawdown agreements. This may include a specific time period for transactions (depending on agreed upon conditions) referred to as a conditions precedent.
A conditions precedent is used to safeguard funds. It requires that certain events take place in order for the contract to be valid. It may also require the submission of certain documentation, including:
- Official documents (such as project agreements) for borrowers and those providing security.
- Proof of authorisations (documents power and capacity) for borrowers and those providing security.
- Licences and consents evidence.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”