Design and build: concept design (design by contractor)
The concept design stage is concerned with preparing a concept design for the preferred option and developing and then freezing the project brief. It may also include making an outline planning application or a detailed planning application. Under this option, all design development is attributed to the contractor, the different disciplines working for the contractor (such as architects or engineers) are not separately identified. We do continue to identify the principal designer as this role is a requirement of the CDM Regulations.
Any design reviews carried out on behalf of the client (or any other advice given to the client) is attributed to independent client advisers. Independent client advisers may previously have been members of the consultant team or could be new appointments if the consultant team have been novated or switched to the contractor.
For concept design by the consultant team see: Design and build: concept design (design by consultant team).
[edit] Starting the work stage.
The client updates the project execution plan to reflect comments made at the end of the previous stage. The contractor co-ordinates a start-up meeting attended by the client to receive comments made at the end of the previous stage and to discuss procedures and the programme for the stage.
The client may identify a requirement to appoint additional independent client advisers (in particular if the consultant team has been novated or switched to the contractor). Go to work stage: Design and build: appointment.
The client may wish to appoint an employer's agent to administer the contract. Go to work stage: Design and build: appointment.
[edit] Preparing an initial concept design.
The contractor carries out any additional site appraisals or surveys that may be necessary.
The contractor co-ordinates the preparation of an initial concept design (including outline specification) and then co-ordinates any necessary consultations with user panels, champions, and other stakeholders, including statutory authorities. The contractor then incorporates comments received into the developing concept design.
The contractor co-ordinates a design review of the concept design and then co-ordinates any necessary amendments to the concept design and amends the elemental cost plan and prepares a cash flow projection.
If necessary the contractor arranges a value management exercise and amends the concept design.
If required by the employer's requirements, the contractor prepares contractor's design documents describing the concept design for the client (such as a concept design report).
The client considers the contractor's design documents and comments within the specified time, either accepting, making comments or rejecting the contractor's design documents. This can only be done in relation to compliance with the employer's requirements. Comments which amount to a change in the employer's requirements must be consented to by the contractor (although this consent may not be unreasonably withheld) and may result in an adjustment to the contract sum and a claim for extension of time.
[edit] If necessary making an outline planning application or detailed planning application.
If no previous applications have been made by the client, the contractor considers whether to make an outline planning application or detailed planning application. Go to work stage: Design and build: planning permission (design by contractor).
Featured articles and news
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.