Design and build: concept design (design by contractor)
The concept design stage is concerned with preparing a concept design for the preferred option and developing and then freezing the project brief. It may also include making an outline planning application or a detailed planning application. Under this option, all design development is attributed to the contractor, the different disciplines working for the contractor (such as architects or engineers) are not separately identified. We do continue to identify the principal designer as this role is a requirement of the CDM Regulations.
Any design reviews carried out on behalf of the client (or any other advice given to the client) is attributed to independent client advisers. Independent client advisers may previously have been members of the consultant team or could be new appointments if the consultant team have been novated or switched to the contractor.
For concept design by the consultant team see: Design and build: concept design (design by consultant team).
[edit] Starting the work stage.
The client updates the project execution plan to reflect comments made at the end of the previous stage. The contractor co-ordinates a start-up meeting attended by the client to receive comments made at the end of the previous stage and to discuss procedures and the programme for the stage.
The client may identify a requirement to appoint additional independent client advisers (in particular if the consultant team has been novated or switched to the contractor). Go to work stage: Design and build: appointment.
The client may wish to appoint an employer's agent to administer the contract. Go to work stage: Design and build: appointment.
[edit] Preparing an initial concept design.
The contractor carries out any additional site appraisals or surveys that may be necessary.
The contractor co-ordinates the preparation of an initial concept design (including outline specification) and then co-ordinates any necessary consultations with user panels, champions, and other stakeholders, including statutory authorities. The contractor then incorporates comments received into the developing concept design.
The contractor co-ordinates a design review of the concept design and then co-ordinates any necessary amendments to the concept design and amends the elemental cost plan and prepares a cash flow projection.
If necessary the contractor arranges a value management exercise and amends the concept design.
If required by the employer's requirements, the contractor prepares contractor's design documents describing the concept design for the client (such as a concept design report).
The client considers the contractor's design documents and comments within the specified time, either accepting, making comments or rejecting the contractor's design documents. This can only be done in relation to compliance with the employer's requirements. Comments which amount to a change in the employer's requirements must be consented to by the contractor (although this consent may not be unreasonably withheld) and may result in an adjustment to the contract sum and a claim for extension of time.
[edit] If necessary making an outline planning application or detailed planning application.
If no previous applications have been made by the client, the contractor considers whether to make an outline planning application or detailed planning application. Go to work stage: Design and build: planning permission (design by contractor).
Featured articles and news
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Refurbishment for net zero; the BSRIA white paper
The everyday practice of tackling energy efficiency, fabric first, ventilation, air quality, and occupant wellbeing.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Stress Awareness Week ends but employer legal duties continue.
A call to follow the five Rs for the business and for the staff.
Key points and relevance to construction of meeting, due to reconvene.
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?