Design and build: concept design (design by contractor)
The concept design stage is concerned with preparing a concept design for the preferred option and developing and then freezing the project brief. It may also include making an outline planning application or a detailed planning application. Under this option, all design development is attributed to the contractor, the different disciplines working for the contractor (such as architects or engineers) are not separately identified. We do continue to identify the principal designer as this role is a requirement of the CDM Regulations.
Any design reviews carried out on behalf of the client (or any other advice given to the client) is attributed to independent client advisers. Independent client advisers may previously have been members of the consultant team or could be new appointments if the consultant team have been novated or switched to the contractor.
For concept design by the consultant team see: Design and build: concept design (design by consultant team).
[edit] Starting the work stage.
The client updates the project execution plan to reflect comments made at the end of the previous stage. The contractor co-ordinates a start-up meeting attended by the client to receive comments made at the end of the previous stage and to discuss procedures and the programme for the stage.
The client may identify a requirement to appoint additional independent client advisers (in particular if the consultant team has been novated or switched to the contractor). Go to work stage: Design and build: appointment.
The client may wish to appoint an employer's agent to administer the contract. Go to work stage: Design and build: appointment.
[edit] Preparing an initial concept design.
The contractor carries out any additional site appraisals or surveys that may be necessary.
The contractor co-ordinates the preparation of an initial concept design (including outline specification) and then co-ordinates any necessary consultations with user panels, champions, and other stakeholders, including statutory authorities. The contractor then incorporates comments received into the developing concept design.
The contractor co-ordinates a design review of the concept design and then co-ordinates any necessary amendments to the concept design and amends the elemental cost plan and prepares a cash flow projection.
If necessary the contractor arranges a value management exercise and amends the concept design.
If required by the employer's requirements, the contractor prepares contractor's design documents describing the concept design for the client (such as a concept design report).
The client considers the contractor's design documents and comments within the specified time, either accepting, making comments or rejecting the contractor's design documents. This can only be done in relation to compliance with the employer's requirements. Comments which amount to a change in the employer's requirements must be consented to by the contractor (although this consent may not be unreasonably withheld) and may result in an adjustment to the contract sum and a claim for extension of time.
[edit] If necessary making an outline planning application or detailed planning application.
If no previous applications have been made by the client, the contractor considers whether to make an outline planning application or detailed planning application. Go to work stage: Design and build: planning permission (design by contractor).
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.