Design and build: planning permission (design by contractor)
Planning permission is a vitally important part of most projects, often making the difference between proceeding to design or not. Many clients will be unwilling to commit to paying fees for detailed design until they have received planning permission, and on particularly high risk projects, the client may even wish to obtain outline planning permission before committing to any significant expenditure. As a consequence planning permission can be applied for at different stages of the project's development.
The allocation of risk for planning permission is an important consideration on design and build projects. Where the contractor is applying for planning permission, delays in obtaining permission (which the contractor has taken reasonable steps to avoid) may be grounds for an extension of time and claims for loss and expense. Delays may even become grounds for termination if they result in the works being suspended.
Contents |
[edit] Assessing the type of application
If it is not specified in the employer's requirements, and no previous application has been made by the client, the contractor considers whether to make an outline planning application or detailed planning application.
Where this has not already been done, the contractor considers the likely need for an environmental impact assessment. They may seek a screening decision and or a scoping study from the local planning authority. If necessary, the contractor prepares an environmental impact assessment.
[edit] Undertaking a consultation process
The contractor consults with the local planning authority (and other appropriate statutory consultees) to determine the preferred form of the application, dates of planning committee meetings, committee procedures, possible planning conditions and possible planning obligations (section 106 agreement), the community infrastructure levy and the requirement to undertake an external consultation process.
The contractor considers the cost effects of statutory requirements and other requirements, including possible planning conditions and planning obligations (section 106 agreement) and, if necessary, amends the design.
The contractors consider the extent and nature of the external consultation process that will be undertaken and then begins an external consultation process. The contractor then considers the results of the consultation process and, if necessary, amends the design. If changes are required to the employer's requirements in order to obtain planning permission, this may result in adjustment of the contract sum and a claim for extension of time by the contractor.
[edit] Preparing a planning application
The contractor co-ordinates the preparation of a draft planning application and issues it to the client for comment.
NB: Comments that require change instructions (i.e. they go beyond pointing out inconsistencies between the design and the employer's requirements), must be consented to by the contractor (although this consent may not be unreasonably withheld) and may result in an adjustment to the contract sum and a claim for extension of time.
The contractor identifies any abnormal costs arising from the draft planning application and if necessary, the contractor co-ordinates amendments to the draft planning application.
[edit] Submitting a planning application
The contractor submits the planning application including the planning fee.
The contractor consults with the local planning authority on the progress of the application and likely planning conditions and planning obligations (section 106 agreement). If necessary, the client and contractor respond to questions from the local planning authority and make representations to the planning committee.
On receipt of a decision (or recommendation in the planning officers' report) the client and contractor consider the planning conditions and planning obligations (section 106 agreement) that have been, or are likely to be, imposed and, if necessary, amends the application.
NB: Comments that constitute change instructions require the consent of the contractor (although this consent may not be unreasonably withheld) and may result in an adjustment to the contract sum and a claim for extension of time.
If necessary, the contractor re-submits the planning application.
Once received, the contractor passes the planning permission (along with details of any planning conditions or planning obligations) to the client. If necessary, a planning appeal may be made against the planning authority decision.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.